PMI Exam PgMP Topic 2 Question 74 Discussion

Actual exam question for PMI's Program Management Professional exam
Question #: 74
Topic #: 2
[All Program Management Professional Questions]

A biometrics firm has a facial recognition program with multiple components and project managers. The

project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring.

What should the program manager do first?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Tamera
2 days ago
I think the program manager should communicate the risk to all project managers to manage at the component level.
upvoted 0 times
...
Levi
24 days ago
Come on, let's be serious here. This is a certification exam, not a game of chance. I think option C is the way to go - adding the risk details to the program risk register is the responsible thing to do.
upvoted 0 times
...
Francene
24 days ago
Haha, can you imagine the program manager just randomly asking the executive sponsor for a risk reserve? 'Excuse me, sir, I need some extra cash just in case a thing might happen.' That's not how it works!
upvoted 0 times
...
Rickie
25 days ago
Yeah, I was thinking the same thing. That way, everyone is aware of the risk and can take appropriate action. But I also think adding the risk details to the program risk register is important for documentation and tracking purposes.
upvoted 0 times
...
Frederica
26 days ago
Haha, that's a good point. Maybe the program manager could throw a coin to decide the next step - heads, they go with option A, tails, option B. That's a risk management strategy, right?
upvoted 0 times
...
Leontine
26 days ago
I agree, that seems like overkill. I think communicating the risk to all the project managers is a good first step, so they can manage it at the component level.
upvoted 0 times
...
Clay
27 days ago
I disagree. Even if the risk has a low impact, it could still have widespread consequences across the program. I think option B is the best choice - communicating the risk to all project managers so they can manage it at the component level.
upvoted 0 times
...
Verdell
27 days ago
Hmm, this is a tricky one. The risk has a low degree of impact and probability, but it could still affect other projects within the program. I'm not sure if getting a risk reserve is the best approach here.
upvoted 0 times
...
Winfred
28 days ago
Hmm, I'm not sure. This risk seems to have a low degree of impact and probability, so I'm not convinced that any of the options are entirely appropriate. Maybe the program manager should just keep an eye on it for now?
upvoted 0 times
...
Xochitl
1 months ago
I agree. This question is assessing our ability to apply risk management principles in a real-world scenario. It's important to be able to make the right decision based on the given information.
upvoted 0 times
Richelle
5 days ago
Obtaining a risk reserve from the executive sponsor and executing a contingency plan is important to have resources ready in case the risk occurs.
upvoted 0 times
...
Laurel
6 days ago
A
upvoted 0 times
...
German
7 days ago
Brainstorming with the project manager to develop an appropriate risk response is essential to come up with effective mitigation strategies.
upvoted 0 times
...
Marylou
8 days ago
D
upvoted 0 times
...
Melita
9 days ago
Communicating the risk to all project managers to manage at the component level ensures that everyone is informed and can take necessary actions.
upvoted 0 times
...
Truman
10 days ago
B
upvoted 0 times
...
Tom
11 days ago
Great choice! Adding the risk details and analysis to the program risk register is a crucial step in managing risks.
upvoted 0 times
...
Leonora
12 days ago
C
upvoted 0 times
...
...
Ronald
1 months ago
This question is testing our understanding of risk management at the program level. I think it's a fair question, as program managers need to know how to prioritize and respond to risks that may impact multiple projects.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77