Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 64 Discussion

Actual exam question for PMI's PMP exam
Question #: 64
Topic #: 3
[All PMP Questions]

When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Jacquelyne
3 days ago
Option B seems like the logical choice here. The project manager should work with the benefit owner to ensure the KPIs are properly defined and tracked.
upvoted 0 times
...
Marshall
12 days ago
I think the project manager should coordinate with the benefit owner to build the KPIs. They are ultimately responsible for the benefits.
upvoted 0 times
...
Sophia
15 days ago
I agree with Jacqueline. It's important to track project benefits accurately.
upvoted 0 times
...
Jacqueline
18 days ago
I think the project manager should work with the business analysts to build the KPIs.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77