The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.
What should the project manager do in this situation?
When a project experiences schedule delays, especially with tasks on the critical path, it is crucial to review the critical path with stakeholders. This collaborative review helps in understanding the impact of the delays and in defining the next steps to mitigate the issues.The stakeholders, including the project team, suppliers, and sponsor, can provide valuable input and decision-making power to help navigate the issues1.
PMBOK Guide -- Sixth Edition2.
''19 Frequently Asked Questions on the Critical Path Method'' by Praveen Malik, PMP3.
'Exam PMP topic 1 question 321 discussion - ExamTopics'1.
''Five Tips for Being Prepared for Supply Chain Disruption'' - PMI.org4.
Limited Time Offer
25%
Off
Horace
11 days agoJina
13 days agoGwenn
15 days agoMari
16 days agoCorazon
18 days agoTina
20 days agoPolly
26 days agoChandra
28 days agoGilberto
6 days agoLachelle
12 days agoAudry
1 months agoKati
22 days agoArminda
26 days agoAmber
28 days ago