The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.
What should the project manager do in this situation?
When a project experiences schedule delays, especially with tasks on the critical path, it is crucial to review the critical path with stakeholders. This collaborative review helps in understanding the impact of the delays and in defining the next steps to mitigate the issues.The stakeholders, including the project team, suppliers, and sponsor, can provide valuable input and decision-making power to help navigate the issues1.
PMBOK Guide -- Sixth Edition2.
''19 Frequently Asked Questions on the Critical Path Method'' by Praveen Malik, PMP3.
'Exam PMP topic 1 question 321 discussion - ExamTopics'1.
''Five Tips for Being Prepared for Supply Chain Disruption'' - PMI.org4.
Limited Time Offer
25%
Off
Horace
2 months agoJina
2 months agoGwenn
2 months agoMari
2 months agoCorazon
2 months agoEden
10 days agoMelissia
11 days agoOra
12 days agoAlonzo
13 days agoRaymon
14 days agoErasmo
19 days agoJeff
22 days agoCatalina
2 months agoTina
2 months agoPolly
3 months agoChandra
3 months agoJanna
2 months agoGilberto
2 months agoLachelle
2 months agoAudry
3 months agoKati
2 months agoArminda
3 months agoAmber
3 months ago