PMI Exam PMP Topic 2 Question 99 Discussion

Actual exam question for PMI's PMP exam
Question #: 99
Topic #: 2
[All PMP Questions]

The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Horace
11 days ago
I believe discussing the critical path issues with the purchasing department can also help address the delays.
upvoted 0 times
...
Jina
13 days ago
I think reviewing the critical path with stakeholders is also important to define next steps.
upvoted 0 times
...
Gwenn
15 days ago
I agree with Mari. The sponsor can help resolve the issues quickly.
upvoted 0 times
...
Mari
16 days ago
I think the project manager should escalate the supplier-related issues to the sponsor.
upvoted 0 times
...
Corazon
18 days ago
I wonder if the project manager has considered hiring a supplier whisperer to smooth things over. Just a thought!
upvoted 0 times
...
Tina
20 days ago
B) Reviewing the WBS with the suppliers is a good idea, but it doesn't directly address the schedule delays on the critical path.
upvoted 0 times
...
Polly
26 days ago
D) Discussing the critical path issues with the purchasing department could help, but I think C) is the most comprehensive solution.
upvoted 0 times
...
Chandra
28 days ago
A) Escalating the supplier-related issues to the sponsor is a smart move. They can apply more pressure to resolve the problems.
upvoted 0 times
Gilberto
6 days ago
B) Reviewing the work breakdown structure with the suppliers could help identify where the issues are coming from.
upvoted 0 times
...
Lachelle
12 days ago
A) Escalating the supplier-related issues to the sponsor is a smart move. They can apply more pressure to resolve the problems.
upvoted 0 times
...
...
Audry
1 months ago
C) Review the critical path with the stakeholders to define next steps. This seems like the best approach to tackle the schedule delays caused by supplier issues.
upvoted 0 times
Kati
22 days ago
C) Review the critical path with the stakeholders to define next steps.
upvoted 0 times
...
Arminda
26 days ago
B) Review the work breakdown structure (WBS) with the suppliers.
upvoted 0 times
...
Amber
28 days ago
A) Escalate the supplier-related issues to the sponsor for resolution.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77