Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 1 Question 98 Discussion

Actual exam question for PMI's PMP exam
Question #: 98
Topic #: 1
[All PMP Questions]

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Show Suggested Answer Hide Answer
Suggested Answer: B

When faced with the aftermath of a failed quality audit, the newly appointed project manager must take several steps to address the situation. Let's explore the options:

1. Perform Integrated Change Control (Option B):

o Integrated change control is a critical process in project management.

o It involves reviewing all change requests, assessing their impact, and making informed decisions about whether to approve or reject them.

o In this case, the failed audit results constitute a change request. The project manager should evaluate the impact of the audit findings, identify necessary corrective actions, and determine whether additional resources (such as new audit resources) are required.

o By performing integrated change control, the project manager ensures that any necessary adjustments are made to the project plan, scope, schedule, and resources.

2. Stakeholder Engagement (Option A):

o While stakeholder engagement is essential, it is not the immediate next step after a failed audit.

o Stakeholder engagement involves ongoing communication and collaboration with stakeholders throughout the project lifecycle.

o The project manager should engage stakeholders, but addressing the audit findings takes precedence.

3. Update the Quality Management Plan (Option C):

o Updating the quality management plan is relevant, but it is a specific response to the audit results.

o The project manager should first assess the impact of the audit findings and then update the quality management plan as needed.

4. Update the Risk Management Plan (Option D):

o While risk management is crucial, it is not the immediate focus after a failed audit.

o The project manager should address the audit findings before revisiting the risk management plan.

In summary, the project manager should prioritize integrated change control to address the audit results, identify corrective actions, and


Contribute your Thoughts:

Camellia
1 months ago
Haha, the workstream leader must be the office jokester or something. Missing deadlines multiple times? That's a recipe for getting fired!
upvoted 0 times
Fatima
13 days ago
C) Workstream leader and functional manager
upvoted 0 times
...
Edwin
14 days ago
B) Workstream leader alone
upvoted 0 times
...
Antione
16 days ago
A) Workstream leader and project sponsor
upvoted 0 times
...
...
Helga
1 months ago
I'm going with D) Workstream leader and PMO. The PMO can offer best practices and project management expertise to get this workstream back on schedule.
upvoted 0 times
...
Elenore
1 months ago
I'm torn between B and C. The workstream leader should definitely be involved, but the functional manager might be able to provide more authority and influence to make the necessary changes.
upvoted 0 times
Herminia
18 days ago
C) Workstream leader and functional manager
upvoted 0 times
...
Virgie
28 days ago
I agree, involving the project sponsor could provide additional support and resources to address the issue.
upvoted 0 times
...
Earleen
1 months ago
A) Workstream leader and project sponsor
upvoted 0 times
...
...
Novella
2 months ago
I agree with C. The functional manager can provide additional oversight and resources to help the workstream leader get the project back on track.
upvoted 0 times
Ardella
24 days ago
That's a good point. The functional manager can definitely provide support in this situation.
upvoted 0 times
...
Mike
1 months ago
C) Workstream leader and functional manager
upvoted 0 times
...
Kaycee
1 months ago
A) Workstream leader and project sponsor
upvoted 0 times
...
...
Aliza
2 months ago
The correct answer is C) Workstream leader and functional manager. It's important to involve the functional manager to ensure accountability and alignment across the organization.
upvoted 0 times
Florinda
28 days ago
User 2: Agreed, involving the functional manager ensures accountability and alignment.
upvoted 0 times
...
Shantay
2 months ago
User 1: The project manager should speak to the workstream leader and functional manager.
upvoted 0 times
...
...
Torie
2 months ago
I think the project manager should also involve the project management office (PMO) to ensure proper governance and oversight.
upvoted 0 times
...
Stephaine
2 months ago
I agree with Veronika. The project sponsor can provide additional support and resources to help meet the deadline.
upvoted 0 times
...
Veronika
3 months ago
I think the project manager should speak to the workstream leader and project sponsor.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77