PMI Exam PMP Topic 1 Question 98 Discussion

Actual exam question for PMI's PMP exam
Question #: 98
Topic #: 1
[All PMP Questions]

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Show Suggested Answer Hide Answer
Suggested Answer: B

When faced with the aftermath of a failed quality audit, the newly appointed project manager must take several steps to address the situation. Let's explore the options:

1. Perform Integrated Change Control (Option B):

o Integrated change control is a critical process in project management.

o It involves reviewing all change requests, assessing their impact, and making informed decisions about whether to approve or reject them.

o In this case, the failed audit results constitute a change request. The project manager should evaluate the impact of the audit findings, identify necessary corrective actions, and determine whether additional resources (such as new audit resources) are required.

o By performing integrated change control, the project manager ensures that any necessary adjustments are made to the project plan, scope, schedule, and resources.

2. Stakeholder Engagement (Option A):

o While stakeholder engagement is essential, it is not the immediate next step after a failed audit.

o Stakeholder engagement involves ongoing communication and collaboration with stakeholders throughout the project lifecycle.

o The project manager should engage stakeholders, but addressing the audit findings takes precedence.

3. Update the Quality Management Plan (Option C):

o Updating the quality management plan is relevant, but it is a specific response to the audit results.

o The project manager should first assess the impact of the audit findings and then update the quality management plan as needed.

4. Update the Risk Management Plan (Option D):

o While risk management is crucial, it is not the immediate focus after a failed audit.

o The project manager should address the audit findings before revisiting the risk management plan.

In summary, the project manager should prioritize integrated change control to address the audit results, identify corrective actions, and


Contribute your Thoughts:

I agree with C. The functional manager can provide additional oversight and resources to help the workstream leader get the project back on track.
upvoted 0 times
...
Aliza
8 days ago
The correct answer is C) Workstream leader and functional manager. It's important to involve the functional manager to ensure accountability and alignment across the organization.
upvoted 0 times
...
Torie
20 days ago
I think the project manager should also involve the project management office (PMO) to ensure proper governance and oversight.
upvoted 0 times
...
Stephaine
21 days ago
I agree with Veronika. The project sponsor can provide additional support and resources to help meet the deadline.
upvoted 0 times
...
Veronika
25 days ago
I think the project manager should speak to the workstream leader and project sponsor.
upvoted 0 times
...

Save Cancel