Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 9 Question 92 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 92
Topic #: 9
[All PMI-SP Questions]

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Eliseo
27 days ago
Let's be honest, the company calendar is probably just a fancy name for the organizational calendar. I'm sticking with C, no need to overthink this.
upvoted 0 times
...
Yolande
28 days ago
Organizational calendar, for sure. It's the one that'll keep all the stakeholders in the loop about those pesky corporate holidays. No more surprises!
upvoted 0 times
...
Elfrieda
1 months ago
The organizational calendar is the way to go. It's like the company's official schedule - can't go wrong with that!
upvoted 0 times
Shawna
4 days ago
C) Organizational calendar
upvoted 0 times
...
Ona
5 days ago
A) Project calendar
upvoted 0 times
...
...
Mose
1 months ago
I'm pretty sure the resource calendar is just for individual team members, not the whole organization. So I'm gonna go with the organizational calendar on this one.
upvoted 0 times
Bernardo
11 days ago
Yeah, the organizational calendar makes the most sense for communicating project timings to stakeholders.
upvoted 0 times
...
Ranee
18 days ago
I agree, the resource calendar is more for individual team members.
upvoted 0 times
...
Chan
1 months ago
I think the project calendar is more specific to the project itself.
upvoted 0 times
...
...
Sherrell
2 months ago
Hmm, I'm torn between the organizational calendar and the company calendar. They both sound like they could work, but I'll go with C just to be safe.
upvoted 0 times
Zena
9 days ago
Yes, the organizational calendar will help stakeholders understand when the project work will take place.
upvoted 0 times
...
Dulce
1 months ago
I agree, it will communicate the project work timings effectively.
upvoted 0 times
...
Rashida
1 months ago
I think the organizational calendar is the right choice.
upvoted 0 times
...
...
Britt
2 months ago
I'm not sure, but I think it could also be A) Project calendar because it specifically relates to the project work.
upvoted 0 times
...
Kasandra
2 months ago
I agree with Cecilia, the organizational calendar makes the most sense.
upvoted 0 times
...
Sue
2 months ago
The organizational calendar seems like the obvious choice here. It's specifically designed to capture all the corporate working hours and holiday schedules.
upvoted 0 times
Aimee
1 months ago
D) Company calendar
upvoted 0 times
...
Freeman
1 months ago
C) Organizational calendar
upvoted 0 times
...
Lonny
2 months ago
B) Resource calendar
upvoted 0 times
...
Kassandra
2 months ago
A) Project calendar
upvoted 0 times
...
...
Cecilia
2 months ago
I think the answer is C) Organizational calendar.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77