You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Eliseo
27 days agoYolande
28 days agoElfrieda
1 months agoShawna
4 days agoOna
5 days agoMose
1 months agoBernardo
11 days agoRanee
18 days agoChan
1 months agoSherrell
2 months agoZena
9 days agoDulce
1 months agoRashida
1 months agoBritt
2 months agoKasandra
2 months agoSue
2 months agoAimee
1 months agoFreeman
1 months agoLonny
2 months agoKassandra
2 months agoCecilia
2 months ago