What project management plan will document the time frame and frequency for the distribution of required information?
The project's Communications Management Plan defines what information will be distributed, when
it will be distributed, to whom it will be
distributed, and the modality of the information.
Answer option D is incorrect. The Schedule Management Plan defines the project work, when the
project work will happen, resource
utilization, and how the schedule will be monitored and controlled.
Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder
Management Plan.
Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be
created, how the changes will be allowed,
how the scope will be executed, monitored and controlled, and finally closed.
Examine the figure given below.
In this project network diagram, what is the total float for Activity I?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?
Beth, the project manager, is responsible for communication with all stakeholders. According to the
PMBOK, the project manager occupies the
center of the interactions between stakeholders and the project itself.
Answer option B is incorrect. Sarah may help with the communications, but she is not responsible
for the communications.
Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the
information.
Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for
communicating with the project
stakeholders.
with the appropriate word. When activities are logically linked, they become the .
__________
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.
A scheduler schedules the constraints for the project into phases with respect to the
time and resources available. He can be hired from
outside a company, or from within a company. The basic roles of a scheduler are as follows:
Feasibility Planning: A scheduler is the time management expert who paints a picture of the project.
He develops a strategy for
delivery and to gain consensus.
Execution Schedule: A scheduler works with the project team to optimize and refine the schedule
until an agreed schedule has been
developed.
Performance Control: A schedule is maintained by the scheduler who optimizes outcomes and
instructs the project team on their
presentation. It is important that the scheduler be aware of the changes and trends related to the
project delivery.
Answer option C is incorrect. This is the skill possessed by the project manager.
Currently there are no comments in this discussion, be the first to comment!