John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the
following activities will he use to make
the schedule models? .
Each correct answer represents a complete solution. Choose all that apply.
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Nan
2 months agoAlyce
2 days agoEzekiel
13 days agoAlton
18 days agoWerner
2 months agoBettina
24 days agoAlethea
1 months agoSabine
1 months agoMarva
2 months agoFrederica
2 days agoMireya
15 days agoBobbye
24 days agoRosalyn
1 months agoAlfred
2 months agoJacquelyne
1 months agoLawanda
2 months agoRikki
2 months agoKiley
2 months agoNieves
2 months agoSarah
2 months ago