PMI Exam PMI-SP Topic 8 Question 69 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 69
Topic #: 8
[All PMI-SP Questions]

You are the project manager for your organization. You are coaching Allen, a junior project manager,

on how the details of the project's critical path are calculated. Examine the figure given below:

What is the critical path of this project?

Show Suggested Answer Hide Answer
Suggested Answer: B

The project's Communications Management Plan defines what information will be distributed, when

it will be distributed, to whom it will be

distributed, and the modality of the information.

Answer option D is incorrect. The Schedule Management Plan defines the project work, when the

project work will happen, resource

utilization, and how the schedule will be monitored and controlled.

Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder

Management Plan.

Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be

created, how the changes will be allowed,

how the scope will be executed, monitored and controlled, and finally closed.


Contribute your Thoughts:

Carmelina
1 months ago
This question is giving me flashbacks to my college engineering classes. Forget the critical path, I just want to know how to build a working robot that can do my job for me. Then I can sit back and enjoy the sweet taste of victory - and a cold, refreshing beverage.
upvoted 0 times
Raymon
18 days ago
That would be nice, but I think we still need to understand the critical path for this project.
upvoted 0 times
...
...
Anisha
1 months ago
Okay, time to put on my project manager hat. After a careful analysis, I believe the correct answer is ACFIJ. Those tasks have the longest duration and must be completed in sequence. Now, if only I could find a way to squeeze in a game of Tetris during the project meetings...
upvoted 0 times
Allene
3 days ago
Let's focus on getting the project done first, then maybe we can sneak in a quick game of Tetris as a reward.
upvoted 0 times
...
Denny
9 days ago
Yes, those tasks definitely have the longest duration and must be completed in sequence. Tetris will have to wait!
upvoted 0 times
...
Dorcas
1 months ago
I think you're right, ACFIJ does seem to be the critical path. Good job analyzing the tasks.
upvoted 0 times
...
...
Brandee
2 months ago
Hold up, I'm getting a bit dizzy just looking at this diagram. But I think the critical path is ABEHJ. It's the longest path without any forks, right? This is why I stick to Scrum - no need for all this critical path nonsense!
upvoted 0 times
Mike
3 days ago
Scrum does simplify project management, but it's still important to understand critical paths in traditional project management.
upvoted 0 times
...
Nichelle
4 days ago
I agree, the critical path is the longest path without any forks.
upvoted 0 times
...
Osvaldo
5 days ago
Yes, you're correct! The critical path is indeed ABEHJ.
upvoted 0 times
...
...
Sueann
2 months ago
I agree with Lelia, ACFGJ seems to be the critical path based on the figure.
upvoted 0 times
...
Lelia
2 months ago
I believe it's ACFGJ because those are the longest duration tasks.
upvoted 0 times
...
Major
2 months ago
I think the critical path is ABEHJ.
upvoted 0 times
...
Franchesca
2 months ago
Hmm, I'm not so sure about that. The figure shows some tasks with multiple predecessors, so I think the critical path might be ADGJ. Gotta watch out for those dependencies!
upvoted 0 times
Leota
5 days ago
I think it might be ACFIJ.
upvoted 0 times
...
Lisbeth
14 days ago
I'm leaning towards ADGJ.
upvoted 0 times
...
Joanna
16 days ago
I believe it's ACFGJ.
upvoted 0 times
...
Nell
27 days ago
No, I believe it's ACFGJ.
upvoted 0 times
...
Xochitl
1 months ago
I think the critical path is ABEHJ.
upvoted 0 times
...
Alfred
1 months ago
I think the critical path is ABEHJ.
upvoted 0 times
...
Amina
1 months ago
No, I believe it's ACFGJ.
upvoted 0 times
...
Odette
1 months ago
I think the critical path is ABEHJ.
upvoted 0 times
...
...
Tyra
2 months ago
I think the critical path is ACFIJ because it includes all the tasks that are essential for completing the project on time.
upvoted 0 times
...
Glen
2 months ago
I disagree, I believe the critical path is ACFGJ.
upvoted 0 times
...
Jeannine
2 months ago
This is a tricky one! The critical path is all about the longest sequence of tasks that must be completed on time. Let's see...ACFGJ looks like the longest path to me.
upvoted 0 times
...
Florinda
2 months ago
I think the critical path of this project is ABEHJ.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77