Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 8 Question 69 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 69
Topic #: 8
[All PMI-SP Questions]

You are the project manager for your organization. You are coaching Allen, a junior project manager,

on how the details of the project's critical path are calculated. Examine the figure given below:

What is the critical path of this project?

Show Suggested Answer Hide Answer
Suggested Answer: B

The project's Communications Management Plan defines what information will be distributed, when

it will be distributed, to whom it will be

distributed, and the modality of the information.

Answer option D is incorrect. The Schedule Management Plan defines the project work, when the

project work will happen, resource

utilization, and how the schedule will be monitored and controlled.

Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder

Management Plan.

Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be

created, how the changes will be allowed,

how the scope will be executed, monitored and controlled, and finally closed.


Contribute your Thoughts:

Sueann
6 days ago
I agree with Lelia, ACFGJ seems to be the critical path based on the figure.
upvoted 0 times
...
Lelia
7 days ago
I believe it's ACFGJ because those are the longest duration tasks.
upvoted 0 times
...
Major
8 days ago
I think the critical path is ABEHJ.
upvoted 0 times
...
Franchesca
8 days ago
Hmm, I'm not so sure about that. The figure shows some tasks with multiple predecessors, so I think the critical path might be ADGJ. Gotta watch out for those dependencies!
upvoted 0 times
...
Tyra
8 days ago
I think the critical path is ACFIJ because it includes all the tasks that are essential for completing the project on time.
upvoted 0 times
...
Glen
11 days ago
I disagree, I believe the critical path is ACFGJ.
upvoted 0 times
...
Jeannine
15 days ago
This is a tricky one! The critical path is all about the longest sequence of tasks that must be completed on time. Let's see...ACFGJ looks like the longest path to me.
upvoted 0 times
...
Florinda
18 days ago
I think the critical path of this project is ABEHJ.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77