PMI Exam PMI-SP Topic 7 Question 64 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 64
Topic #: 7
[All PMI-SP Questions]

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Osvaldo
1 months ago
Scope verification? More like 'scope creep verification'! Am I right, or am I right? Anyway, I'm going with configuration management system on this one.
upvoted 0 times
Keneth
6 days ago
I agree, scope creep can really throw a project off track.
upvoted 0 times
...
...
Sabine
2 months ago
Project management information system? Nah, that's just a fancy way of saying 'the big binder of doom' that no one ever looks at. Gotta be configuration management all the way!
upvoted 0 times
Rosalind
12 days ago
Integrated change control is also important for authorizing and controlling changes.
upvoted 0 times
...
Ernie
14 days ago
Yeah, the big binder of doom is definitely not the most efficient way to manage changes.
upvoted 0 times
...
Roslyn
1 months ago
I agree, configuration management is key for controlling changes.
upvoted 0 times
...
...
Matt
2 months ago
Integrated change control? That's got to be it! I mean, who doesn't love a good change control system with all the bells and whistles?
upvoted 0 times
...
Jani
2 months ago
I'm pretty sure the answer is configuration management system. Gotta have those approval levels and documentation to keep things from spiraling out of control, am I right?
upvoted 0 times
Keneth
3 days ago
Yeah, without proper documentation and tracking systems, changes can easily cause chaos.
upvoted 0 times
...
Erinn
10 days ago
I think you're right, it's definitely important to have those approval levels in place.
upvoted 0 times
...
Rebbeca
1 months ago
Integrated Change Control also plays a key role in ensuring changes are properly managed and approved.
upvoted 0 times
...
Joesph
1 months ago
I agree, the configuration management system is crucial for authorizing and controlling changes.
upvoted 0 times
...
Moon
1 months ago
Yeah, without proper documentation and tracking systems, changes can easily get out of hand.
upvoted 0 times
...
Charlene
1 months ago
I think you're right, it's definitely important to have those approval levels in place.
upvoted 0 times
...
...
Rima
2 months ago
I'm not sure, but I think it's between B) Configuration Management System and D) Integrated Change Control.
upvoted 0 times
...
Arlette
2 months ago
I agree with Scarlet. Integrated Change Control includes all the necessary components for authorizing and controlling changes.
upvoted 0 times
...
Frederic
2 months ago
Ooh, this one's a tricky one! I bet it's got something to do with all that paperwork we've been drowning in. Let's see, where do we keep track of all those changes we've been making?
upvoted 0 times
Georgiana
23 days ago
B) Configuration Management System
upvoted 0 times
...
Man
1 months ago
C) Project Management Information System
upvoted 0 times
...
Karol
1 months ago
D) Integrated Change Control
upvoted 0 times
...
Peggie
2 months ago
B) Configuration Management System
upvoted 0 times
...
...
Scarlet
3 months ago
I think the answer is D) Integrated Change Control.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77