PMI Exam PMI-SP Topic 6 Question 97 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 97
Topic #: 6
[All PMI-SP Questions]

Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Beula
27 days ago
You know, this reminds me of that time I accidentally spilled paint on my cat. Good times, good times.
upvoted 0 times
...
Michael
28 days ago
I don't know, guys. All this talk about painting and carpets is making me hungry. Anyone up for a paint-themed snack break?
upvoted 0 times
...
Wilda
1 months ago
Okay, let's see. A and D just seem like Band-Aids, but C? That's thinking outside the box. I bet Joe's going to get a raise for this one.
upvoted 0 times
Carrol
12 days ago
I agree, adding a dummy activity seems like the best solution.
upvoted 0 times
...
...
Tegan
1 months ago
Hmm, I was leaning towards B, but now I'm not so sure. Maybe C is the way to go. It's like a magical time-keeper activity!
upvoted 0 times
...
Eleonore
2 months ago
Option C looks like the perfect solution. A dummy activity to account for the drying time? Genius!
upvoted 0 times
Pa
2 days ago
It's important to have that buffer time between painting and carpeting.
upvoted 0 times
...
Jules
3 days ago
Adding a dummy activity for the drying process is a smart move.
upvoted 0 times
...
Jina
7 days ago
I agree, option C seems like the most practical solution.
upvoted 0 times
...
...
Desmond
2 months ago
I think creating a dummy activity for the drying process is the most effective solution.
upvoted 0 times
...
Laquita
2 months ago
I disagree, I believe changing the relationship to finish-to-finish is the way to go.
upvoted 0 times
...
Kasandra
3 months ago
I think the best approach is to add lead time to the painting activity.
upvoted 0 times
...