Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 80 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 80
Topic #: 6
[All PMI-SP Questions]

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Jettie
1 days ago
The milestone list sounds like it would be really helpful for this process. I can't imagine trying to sequence activities without that.
upvoted 0 times
...
Henriette
16 days ago
Hmm, I see your point. But I still think it's B) Milestone list because we need that for tracking project progress.
upvoted 0 times
...
Mickie
18 days ago
Hmm, the project scope statement is definitely one of the key inputs for activity sequencing. I'm pretty sure that's a must-have document.
upvoted 0 times
...
Gracia
19 days ago
I disagree, I believe the answer is C) Project schedule network diagrams.
upvoted 0 times
...
Henriette
20 days ago
I think the answer is B) Milestone list.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77