Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 80 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 80
Topic #: 6
[All PMI-SP Questions]

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Kristian
1 months ago
Ah, the project scope statement. The one document that's thicker than the entire project plan. No wonder they don't want us to use that one.
upvoted 0 times
...
Viva
1 months ago
Wait, we need to sequence the activities? I thought we were just going to throw them all in a hat and draw them out randomly. Where's the fun in that?
upvoted 0 times
Helaine
9 days ago
C) Project schedule network diagrams
upvoted 0 times
...
Margart
13 days ago
B) Milestone list
upvoted 0 times
...
Tamesha
19 days ago
A) Project scope statement
upvoted 0 times
...
...
Chauncey
1 months ago
Project schedule network diagrams? That's a new one. I guess the project manager is really going for the advanced level here.
upvoted 0 times
Desire
12 days ago
C) Project schedule network diagrams
upvoted 0 times
...
Moon
18 days ago
B) Milestone list
upvoted 0 times
...
Abraham
1 months ago
A) Project scope statement
upvoted 0 times
...
...
Glory
2 months ago
Ah, the activity list is a no-brainer. How can you sequence activities without the actual list of activities? It's like trying to bake a cake without ingredients.
upvoted 0 times
Ashley
13 days ago
User 3: Agreed, it's like trying to bake a cake without ingredients.
upvoted 0 times
...
Anissa
15 days ago
User 2: Yeah, that makes sense. You can't sequence activities without the actual list of activities.
upvoted 0 times
...
Marylou
19 days ago
User 1: I think the answer is D) Activity list.
upvoted 0 times
...
...
Jettie
2 months ago
The milestone list sounds like it would be really helpful for this process. I can't imagine trying to sequence activities without that.
upvoted 0 times
Shakira
2 days ago
D) Activity list
upvoted 0 times
...
Gabriele
17 days ago
C) Project schedule network diagrams
upvoted 0 times
...
Domitila
1 months ago
B) Milestone list
upvoted 0 times
...
Mitzie
2 months ago
A) Project scope statement
upvoted 0 times
...
...
Henriette
2 months ago
Hmm, I see your point. But I still think it's B) Milestone list because we need that for tracking project progress.
upvoted 0 times
...
Mickie
2 months ago
Hmm, the project scope statement is definitely one of the key inputs for activity sequencing. I'm pretty sure that's a must-have document.
upvoted 0 times
Leana
18 days ago
D) Activity list
upvoted 0 times
...
Wilda
21 days ago
C) Project schedule network diagrams
upvoted 0 times
...
Alica
2 months ago
B) Milestone list
upvoted 0 times
...
Teddy
2 months ago
A) Project scope statement
upvoted 0 times
...
...
Gracia
2 months ago
I disagree, I believe the answer is C) Project schedule network diagrams.
upvoted 0 times
...
Henriette
2 months ago
I think the answer is B) Milestone list.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77