Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 75 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 75
Topic #: 5
[All PMI-SP Questions]

You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $425,000 of the budget. Management wants to know what the project's cost performance index is. What value do you report?

Show Suggested Answer Hide Answer
Suggested Answer: D

Beth, the project manager, is responsible for communication with all stakeholders. According to the

PMBOK, the project manager occupies the

center of the interactions between stakeholders and the project itself.

Answer option B is incorrect. Sarah may help with the communications, but she is not responsible

for the communications.

Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the

information.

Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for

communicating with the project

stakeholders.


Contribute your Thoughts:

Hyun
2 months ago
Wait, wait, wait... did the question say the project budget is $875,000 and they've spent $425,000? That sounds like a recipe for disaster! I'll go with C. .82.
upvoted 0 times
Annita
5 days ago
D) -$187,500
upvoted 0 times
...
Coral
15 days ago
C) .82
upvoted 0 times
...
Lacey
23 days ago
C) .82
upvoted 0 times
...
Tarra
29 days ago
B) $350,000
upvoted 0 times
...
Nohemi
1 months ago
B) $350,000
upvoted 0 times
...
Magdalene
1 months ago
A) -$75,000
upvoted 0 times
...
Leonor
1 months ago
A) -$75,000
upvoted 0 times
...
...
Kate
2 months ago
Haha, I bet the project manager is wishing they had a time machine to go back and fix those errors! Anyway, I'm going with D. -$187,500.
upvoted 0 times
...
Verona
2 months ago
Ugh, I'm not sure about this one. Too many numbers to keep track of. Maybe I should have paid more attention in my project management class.
upvoted 0 times
Robt
25 days ago
C) .82
upvoted 0 times
...
Marquetta
1 months ago
A) -$75,000
upvoted 0 times
...
...
Erinn
2 months ago
I would go with C) .82 as well, it shows that we are not performing as well as we should be
upvoted 0 times
...
William
2 months ago
Hmm, I think the answer is C. .82. That's the cost performance index, which is the ratio of the budgeted cost of work performed to the actual cost of work performed. Simple enough!
upvoted 0 times
...
Nadine
2 months ago
I agree with Sophia, .82 makes sense because we are behind schedule and over budget
upvoted 0 times
...
Sophia
2 months ago
I think the cost performance index is C) .82
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77