Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?
Stakeholders are interviewed and can help identify other stakeholders that should be
included in the project communications.
Answer option B is incorrect. According to the PMBOK, this is not the best answer.
Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by
it.
Answer option C is incorrect. Project customers are stakeholders.