You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start- to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?
The limit on each work is an organizational policy for each project. Policies, rules, and
organizational requirements are the enterprise
environmental factors.
Answer option D is incorrect. Organizational process assets are things that have been created for the
project manager, such as software,
templates, guidelines, and other resources that will assist the project manager in completing the
project.
Answer option C is incorrect. While this could be a resource limitation, it is not a valid project
management term. Resource leveling heuristics
or a project constraint would have been acceptable answers.
Answer option A is incorrect. Expert judgment happens, when the project manager relies on
someone with more knowledge on a topic to help
the project manager make the best project decision.
Scarlet
1 months agoNoah
1 months agoJulianna
5 days agoWynell
14 days agoKimberely
1 months agoKallie
2 months agoSommer
4 days agoStevie
5 days agoSarah
13 days agoPamela
2 months agoGianna
11 days agoLou
12 days agoDana
13 days agoJacquline
23 days agoJules
2 months agoBritt
2 months agoErnest
12 days agoVenita
13 days agoFranklyn
14 days agoBuck
15 days agoTheresia
17 days agoNoah
19 days agoJaclyn
20 days agoKimberely
1 months agoBrice
3 months agoStephanie
3 months ago