Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 2 Question 84 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 84
Topic #: 2
[All PMI-SP Questions]

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Julieta
2 months ago
Ah, the joys of project management! This question reminds me of the time I had to calculate the SPI for a project that was running behind schedule because the team kept getting distracted by office ping-pong tournaments. Gotta love it! Anyway, I think B) 0.75 is the correct answer, but I might be a little biased since I'm the office ping-pong champion.
upvoted 0 times
Tiera
5 days ago
C) 0.95
upvoted 0 times
...
Lynette
9 days ago
B) 0.75
upvoted 0 times
...
Elizabeth
1 months ago
A) $227,140
upvoted 0 times
...
...
Lashandra
2 months ago
I'm scratching my head on this one. The question says the project is running late by 10%, but it doesn't give us the original planned schedule. How are we supposed to calculate the SPI without that information? I'm going to go with B) 0.75, but I'm not totally confident about it.
upvoted 0 times
Chu
12 days ago
D) -$56,789
upvoted 0 times
...
Long
18 days ago
C) 0.95
upvoted 0 times
...
Lizette
1 months ago
B) 0.75
upvoted 0 times
...
Frederick
1 months ago
A) $227,140
upvoted 0 times
...
...
Shalon
2 months ago
Okay, let's think this through step-by-step. The project is 30% complete, and the BAC is $567,899. So the planned value (PV) should be 30% of $567,899, which is $170,369.70. The actual cost (AC) is $179,450. Plugging these values into the SPI formula, we get 0.75. Looks like B) is the right answer.
upvoted 0 times
Stefania
1 months ago
Yes, that's correct. The SPI is 0.75.
upvoted 0 times
...
Caitlin
1 months ago
I think the SPI is 0.75.
upvoted 0 times
...
...
Renea
2 months ago
This question is testing our knowledge of the Schedule Performance Index (SPI), which is a crucial metric for project managers. I think the correct answer is B) 0.75, as this aligns with the project being 30% complete and having spent $179,450 out of a total BAC of $567,899.
upvoted 0 times
Jennie
18 days ago
D) -$56,789
upvoted 0 times
...
Tegan
20 days ago
C) 0.95
upvoted 0 times
...
Francesco
21 days ago
B) 0.75
upvoted 0 times
...
Kayleigh
1 months ago
A) $227,140
upvoted 0 times
...
...
Elfriede
2 months ago
I'm not sure about this one. Can someone explain how they got to 0.75?
upvoted 0 times
...
Vincent
2 months ago
I agree with Lenna. The SPI formula is EV / PV, so it should be 0.75.
upvoted 0 times
...
Lenna
3 months ago
I think the answer is B) 0.75.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77