PMI Exam PMI-SP Topic 2 Question 74 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 74
Topic #: 2
[All PMI-SP Questions]

You are the project manager for your company. You are working with the activities defined in the figure below.

What will happen to your project if Activity F takes five additional days to complete than what was expected?

Show Suggested Answer Hide Answer
Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Contribute your Thoughts:

Laquita
1 months ago
Ah, the joys of project management. It's like a game of Tetris, but with deadlines instead of blocks. I'll go with B and hope the client doesn't throw a fit.
upvoted 0 times
...
Dominga
2 months ago
Two critical paths? That's like having two left feet - it's just not going to work. D is definitely not the way to go here.
upvoted 0 times
Kimberely
2 days ago
B) Your project will be late by five days.
upvoted 0 times
...
Ammie
4 days ago
A) Your project's critical path will shift to ACFI.
upvoted 0 times
...
...
Weldon
2 months ago
I don't know about you guys, but I'm feeling a bit float-y after looking at this question. All joking aside, I think C is the correct answer here.
upvoted 0 times
Walker
3 days ago
That's a good point, so maybe C is the correct answer after all.
upvoted 0 times
...
Hortencia
1 months ago
But if there is float available on Activity I, then the project can still complete on time.
upvoted 0 times
...
Tess
1 months ago
I think it might actually be D, since Activity F is on the critical path.
upvoted 0 times
...
Thad
2 months ago
I agree, C seems like the best option.
upvoted 0 times
...
...
Anisha
2 months ago
Five extra days for Activity F? That's going to put a serious dent in the project's timeline. B is the way to go, no doubt about it.
upvoted 0 times
Bettina
1 months ago
Five extra days for Activity F? That's going to put a serious dent in the project's timeline. B is the way to go, no doubt about it.
upvoted 0 times
...
Jenelle
1 months ago
A) Your project's critical path will shift to ACFI.
upvoted 0 times
...
...
Cassie
2 months ago
Looks like Activity F is the culprit here. Shifting the critical path to ACFI seems like the obvious choice, but I wonder if the float on Activity I can really save the day.
upvoted 0 times
Kanisha
19 days ago
So, it's better to plan for the worst-case scenario and adjust accordingly.
upvoted 0 times
...
Narcisa
23 days ago
I'm not sure, but if Activity F takes five additional days, the project will be late by five days.
upvoted 0 times
...
Avery
1 months ago
But what if the float on Activity I can actually save the day?
upvoted 0 times
...
Belen
1 months ago
I think shifting the critical path to ACFI is the best option.
upvoted 0 times
...
...
Marti
2 months ago
But won't the critical path shift to ACFI if Activity F is delayed?
upvoted 0 times
...
Mirta
2 months ago
I disagree, I believe our project can still complete on time as float is available on Activity I.
upvoted 0 times
...
Marti
3 months ago
I think if Activity F takes five additional days, our project will be late by five days.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77