Several issues are identified on one component project in a program. During a meeting with that component's project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.
What should the program manager do?
Jeanice
27 days agoRose
29 days agoRoy
1 months agoMariann
9 days agoDalene
1 months agoJanna
16 days agoNgoc
18 days agoKyoko
2 months agoReena
13 days agoKenny
18 days agoTony
1 months agoKristel
2 months agoSerina
2 months agoMaxima
3 months ago