A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?
Ah, tricky one! I was debating between B) Program scope management plan and C) Program risk management plan, but I guess the risk plan is the way to go.
Hmm, I was leaning towards D) Component project risk register, but I can see how the program-level risk management plan would be more appropriate here.
I think the correct answer is C) Program risk management plan. That's where you document and monitor risks, including opportunities like this new program component.
I think the Program scope management plan could also be used to document and monitor the opportunity, as it outlines the scope of the program and its components.
Kimbery
1 months agoKandis
1 months agoErinn
12 days agoGalen
14 days agoElsa
17 days agoViola
1 months agoMirta
2 months agoVi
14 days agoLyda
18 days agoShawna
19 days agoCherelle
2 months agoIdella
Jeanice
5 days agoElly
18 days agoAllene
1 months agoLisha
1 months agoNatalie
2 months agoRefugia
1 months agoAdolph
1 months agoBilly
2 months agoPhung
3 months agoLera
3 months ago