PMI Exam PgMP Topic 3 Question 76 Discussion

Actual exam question for PMI's PgMP exam
Question #: 76
Topic #: 3
[All PgMP Questions]

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind

schedule. Based on this information, what is the schedule performance index (SPI) for this program?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Kimbery
1 months ago
Is it just me, or does this program manager need to work on their time management skills? *shakes head* Gotta stay on top of those schedules, folks.
upvoted 0 times
...
Lizbeth
1 months ago
Piece of cake! The SPI is 0.86, and that's option D. *high-fives* These kinds of questions are my bread and butter.
upvoted 0 times
Tyra
16 days ago
Great work! Option D, with an SPI of 0.86, is the correct answer.
upvoted 0 times
...
Elza
18 days ago
Nice job! You're right, the SPI is 0.86.
upvoted 0 times
...
Bea
1 months ago
I think the SPI is 0.86, so option D is the correct answer.
upvoted 0 times
...
...
Muriel
2 months ago
Ah, I got it! The SPI is 0.86, which means the program is behind schedule. *chuckles* I wonder if the project manager is sweating bullets right now.
upvoted 0 times
Cathrine
8 days ago
D) .89
upvoted 0 times
...
Leslee
9 days ago
C) 1.05
upvoted 0 times
...
Darrin
16 days ago
B) .86
upvoted 0 times
...
Melynda
1 months ago
A) $821,065
upvoted 0 times
...
...
Twana
2 months ago
Wait, are we supposed to calculate the SPI or just identify it from the options? I better double-check the question.
upvoted 0 times
...
Delfina
2 months ago
I also believe the answer is B) .86, as the SPI indicates how efficiently the program is progressing in relation to the planned schedule
upvoted 0 times
...
Lauran
2 months ago
I agree with Shala, because SPI is calculated by dividing percent complete by percent planned, which in this case is 30% / 35% = .86
upvoted 0 times
...
Talia
2 months ago
Hmm, this seems straightforward. I'll go with option B, that's the schedule performance index (SPI) for this program.
upvoted 0 times
Dorsey
14 days ago
User 3: That makes sense, .86 is the SPI for this program
upvoted 0 times
...
Frank
18 days ago
User 2: I agree, option B is the correct answer
upvoted 0 times
...
Britt
2 months ago
User 1: I think the SPI is .86
upvoted 0 times
...
...
Shala
2 months ago
I think the answer is B) .86
upvoted 0 times
...
Mitsue
2 months ago
I also believe the answer is B) .86, as the SPI indicates how efficiently the program is progressing compared to the planned schedule
upvoted 0 times
...
Reita
3 months ago
I agree with Vincent, because SPI is calculated by dividing percent complete by percent planned, which in this case is 30% / 35% = .86
upvoted 0 times
...
Vincent
3 months ago
I think the answer is B) .86
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77