Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 3 Question 76 Discussion

Actual exam question for PMI's PgMP exam
Question #: 76
Topic #: 3
[All PgMP Questions]

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind

schedule. Based on this information, what is the schedule performance index (SPI) for this program?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Muriel
4 days ago
Ah, I got it! The SPI is 0.86, which means the program is behind schedule. *chuckles* I wonder if the project manager is sweating bullets right now.
upvoted 0 times
...
Twana
5 days ago
Wait, are we supposed to calculate the SPI or just identify it from the options? I better double-check the question.
upvoted 0 times
...
Delfina
10 days ago
I also believe the answer is B) .86, as the SPI indicates how efficiently the program is progressing in relation to the planned schedule
upvoted 0 times
...
Lauran
16 days ago
I agree with Shala, because SPI is calculated by dividing percent complete by percent planned, which in this case is 30% / 35% = .86
upvoted 0 times
...
Talia
18 days ago
Hmm, this seems straightforward. I'll go with option B, that's the schedule performance index (SPI) for this program.
upvoted 0 times
...
Shala
19 days ago
I think the answer is B) .86
upvoted 0 times
...
Mitsue
21 days ago
I also believe the answer is B) .86, as the SPI indicates how efficiently the program is progressing compared to the planned schedule
upvoted 0 times
...
Reita
24 days ago
I agree with Vincent, because SPI is calculated by dividing percent complete by percent planned, which in this case is 30% / 35% = .86
upvoted 0 times
...
Vincent
25 days ago
I think the answer is B) .86
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77