You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
Miriam
23 days agoJani
25 days agoOdelia
6 days agoSabine
1 months agoJerlene
2 months agoPenney
4 days agoGabriele
6 days agoAlline
10 days agoFranklyn
29 days agoWilda
1 months agoAilene
1 months agoWilbert
2 months agoProvidencia
2 months agoWilda
2 months ago