GIAC Exam GCPM Topic 3 Question 68 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 68
Topic #: 3
[All GCPM Questions]

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Miriam
23 days ago
Hmm, let's see... If the project is 45% complete but should be 49%, that's gotta mean the CPI is less than 1. Aha, it's C!
upvoted 0 times
...
Jani
25 days ago
Hold up, I'm getting some serious deja vu here. Didn't we do a similar problem last week? Oh well, time to put on my project management hat and crunch those numbers.
upvoted 0 times
Odelia
6 days ago
A) 1.06
upvoted 0 times
...
...
Sabine
1 months ago
Okay, let's break this down. BAC of $945,000, 45% complete, and $455,897 spent... Yup, that's gotta be option C for sure.
upvoted 0 times
...
Jerlene
2 months ago
Haha, the project manager's trying to pull a fast one with that contingency response! Let's see if they can keep their CPI under 0.93.
upvoted 0 times
Penney
4 days ago
B) 0.93
upvoted 0 times
...
Gabriele
6 days ago
Haha, that project manager is definitely trying to play it safe with that contingency response!
upvoted 0 times
...
Alline
10 days ago
A) 1.06
upvoted 0 times
...
Franklyn
29 days ago
C) 0.92
upvoted 0 times
...
Wilda
1 months ago
B) 0.93
upvoted 0 times
...
Ailene
1 months ago
A) 1.06
upvoted 0 times
...
...
Wilbert
2 months ago
I calculated the cost performance index to be 0.92 based on the given information.
upvoted 0 times
...
Providencia
2 months ago
I agree, the project is behind schedule and over budget.
upvoted 0 times
...
Wilda
2 months ago
I think the cost performance index should be less than 0.93.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77