Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

The Open Group Exam OG0-091 Topic 2 Question 81 Discussion

Actual exam question for The Open Group's OG0-091 exam
Question #: 81
Topic #: 2
[All OG0-091 Questions]

In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Eura
6 days ago
Hmm, I'm leaning towards Phase F. That's where you coordinate all the different frameworks, right? Gotta make sure everything plays nice together.
upvoted 0 times
...
Meaghan
7 days ago
I'm pretty sure it's Phase E, where the actual implementation happens. The migration plan is a key part of that phase.
upvoted 0 times
...
Lisbeth
23 days ago
Hmm, you might be right. Let's review the material again to be sure.
upvoted 0 times
...
Honey
24 days ago
I disagree, I believe it's Phase F because that's where the migration plan is finalized.
upvoted 0 times
...
Lisbeth
25 days ago
I think it's Phase E because that's where all the implementation happens.
upvoted 0 times
...

Save Cancel