Question #: 10
Topic #: 1
[All CIS-SPM Questions]

What is a resource event?

Show Suggested Answer Hide Answer
Suggested Answer: B

A resource event is a non-scheduled activity that affects the availability and capacity of a resource or a group of resources. Examples of resource events are vacations, holidays, training, or sick leave. Resource events can be created by resource managers or resources themselves, and they can be viewed in the resource calendar or the resource workbench. You can find more information about resource events in theProduct Documentationfor ServiceNow.


Contribute your Thoughts:

Dominque
1 years ago
I think it's a combination of all options, depending on the context.
upvoted 0 times
...
Lashawnda
1 years ago
I disagree, I think it's an event scheduled by a project manager.
upvoted 0 times
...
Harrison
1 years ago
I believe it can also be an external event that impacts capacity.
upvoted 0 times
...
Talia
1 years ago
I agree with I also think it's a block of time spent on a task.
upvoted 0 times
...
Louis
1 years ago
I think a resource event is when a resource spends time on a task.
upvoted 0 times
...
Carmela
1 years ago
I agree with Belen, I think a resource event is more along the lines of an external event that affects a resource. Like if a team member has a family emergency or a piece of equipment breaks down unexpectedly.
upvoted 0 times
...
Belen
1 years ago
You know, I'm starting to think that none of these options are quite right. Maybe a resource event is something more like an external event that impacts the availability or assignment of a resource. Just a thought.
upvoted 0 times
...
Benton
1 years ago
Hmm, I'm not so sure. I was thinking it might be option D, an event scheduled by a project manager. That would make sense as a resource event, since the project manager is the one who's responsible for scheduling and managing resources.
upvoted 0 times
...
Rima
1 years ago
I'm leaning towards option C. A block of time that a resource spends on a task seems like the most straightforward definition of a resource event. After all, that's what we're really interested in when managing projects, right?
upvoted 0 times
Hoa
1 years ago
I'm not sure about option D. It seems too specific to be the definition of a resource event.
upvoted 0 times
...
Willow
1 years ago
I think option B could also be a valid definition. It's non-scheduled and impacts capacity.
upvoted 0 times
...
Jeanice
1 years ago
I agree, option C does seem like the most logical choice.
upvoted 0 times
...
...
Rory
1 years ago
I think it's option B. A non-scheduled activity that impacts capacity sounds like it could be a resource event, like a team member having to attend a last-minute meeting or an unexpected equipment failure.
upvoted 0 times
...
Adell
1 years ago
Hmm, this is a tricky one. I'm not entirely sure about the definition of a resource event. Is it something to do with the time a resource spends on a task, or is it a non-scheduled activity that impacts capacity?
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77