Question #: 92
Topic #: 1
[All SMC Questions]

Between traditional Project Management and Scrum, differences exist in how quality is achieved and/or

implemented. In this respect, which of the following is NOT true?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Willodean
29 days ago
Wow, I'm surprised they're even asking about this. It's like they want us to be mind readers or something!
upvoted 0 times
...
Ahmed
1 months ago
Option D is definitely true. In Scrum, the product development is carried out in short iterations called Sprints.
upvoted 0 times
Grover
13 days ago
B) In traditional project management, changes can be made only through a formal change management system.
upvoted 0 times
...
Audra
14 days ago
A) In traditional project management, once the user clarifies their quality expectations, it is the Project Manager who defines those user expectations in measurable terms.
upvoted 0 times
...
...
Lenna
1 months ago
I agree with option C. In Scrum, the Scrum Master and the Scrum Team collaborate to define the Acceptance Criteria for the User Stories.
upvoted 0 times
Tamra
4 days ago
I agree with you, option D is not true. In Scrum, the development of the product is carried out by the Scrum Team in short iterations called Sprints.
upvoted 0 times
...
Verona
13 days ago
I disagree, I believe option B is not true. Changes can be made in traditional project management without going through a formal change management system.
upvoted 0 times
...
Anissa
17 days ago
I think option A is not true. In traditional project management, it is the Project Manager who defines the user expectations in measurable terms.
upvoted 0 times
...
...
Annita
1 months ago
Option B seems accurate to me. In traditional project management, changes can only be made through a formal change management system.
upvoted 0 times
Talia
2 days ago
C) In Scrum, the Scrum Master and the Scrum Team collaborate and decide on the Acceptance Criteria for the User Stories.
upvoted 0 times
...
Margarita
4 days ago
B) In traditional project management, changes can be made only through a formal change management system.
upvoted 0 times
...
Carman
1 months ago
A) In traditional project management, once the user clarifies their quality expectations, it is the Project Manager who defines those user expectations in measurable terms.
upvoted 0 times
...
...
Willard
2 months ago
But in Scrum, the Scrum Master and the Scrum Team collaborate on Acceptance Criteria, so C could also be correct.
upvoted 0 times
...
Meaghan
2 months ago
I think option A is not correct. In traditional project management, the project manager defines the quality expectations, not the user.
upvoted 0 times
Margarett
16 days ago
User 4: So, option A is NOT true.
upvoted 0 times
...
Huey
22 days ago
User 3: That's true, the user clarifies their expectations and the project manager defines them.
upvoted 0 times
...
Justine
2 months ago
User 2: In traditional project management, the project manager defines the quality expectations, not the user.
upvoted 0 times
...
Ruthann
2 months ago
User 1: I think option A is not correct.
upvoted 0 times
...
...
Johana
2 months ago
I disagree, I believe the answer is B.
upvoted 0 times
...
Willard
2 months ago
I think the answer is A.
upvoted 0 times
...