Which of the following best describes why Epics are decomposed into smaller User Stories during a Sprint?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Viva
1 months ago
You know, if Epics were the size of those thick fantasy novels, the poor Product Owner would need a forklift to get them into the Sprint planning meeting.
upvoted 0 times
Eileen
14 hours ago
C) Too large to be completed in a Sprint.
upvoted 0 times
...
Amina
3 days ago
A) Tasks are easier to complete.
upvoted 0 times
...
...
Elenore
2 months ago
Haha, I bet the Scrum Masters love it when Epics are the size of novels. 'Just knock that out in two weeks, team!' Not a chance!
upvoted 0 times
Lynette
1 months ago
Yeah, breaking down those Epics into smaller User Stories definitely helps us get things done in a Sprint.
upvoted 0 times
...
Alaine
1 months ago
C) Too large to be completed in a Sprint.
upvoted 0 times
...
Sunshine
1 months ago
A) Tasks are easier to complete.
upvoted 0 times
...
...
Elfriede
2 months ago
I was going to say Option A, but then I realized that's not quite right. Smaller tasks aren't the goal, but rather being able to finish the work within the Sprint.
upvoted 0 times
Janet
1 months ago
Agreed. Option A might sound right at first, but it's really about the size of the work.
upvoted 0 times
...
Daryl
1 months ago
Definitely. It's all about being able to finish the work within the Sprint.
upvoted 0 times
...
Lea
1 months ago
That makes sense. Breaking them down into smaller User Stories helps with that.
upvoted 0 times
...
Milly
2 months ago
I think the answer is C. Epics are too large to be completed in a Sprint.
upvoted 0 times
...
...
Gilma
2 months ago
I agree with Mindy. Epics are just too large to be tackled in a single Sprint. Breaking them down makes the work more manageable.
upvoted 0 times
Tawanna
1 months ago
Agreed, breaking down Epics into smaller User Stories definitely makes the work more manageable.
upvoted 0 times
...
Naomi
1 months ago
I think C) Too large to be completed in a Sprint is the best option.
upvoted 0 times
...
...
Mindy
2 months ago
Option C is the correct answer. Epics are broken down into smaller User Stories to ensure they can be completed within a single Sprint.
upvoted 0 times
...
Minna
2 months ago
D) Take considerably longer time to review. Breaking down Epics helps in faster review and feedback.
upvoted 0 times
...
Eladia
2 months ago
I agree with Linwood. Epics need to be broken down into smaller User Stories to be manageable within a Sprint.
upvoted 0 times
...
Linwood
2 months ago
C) Too large to be completed in a Sprint.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77