ScrumStudy Exam SMC Topic 1 Question 106 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 106
Topic #: 1
[All SMC Questions]

A CEO asks the Development Team to add a new item to the Sprint. What should the Development Team do in response?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Adding the item directly to the Sprint without the Product Owner's input? Sounds like a recipe for disaster!
upvoted 0 times
...
Kattie
12 days ago
The Development Team should refer the new item to the Product Owner. That's the proper Scrum process.
upvoted 0 times
...
Gearldine
16 days ago
D) Add the item to the Product Backlog
upvoted 0 times
...
Colette
17 days ago
B) Add the item to the Sprint
upvoted 0 times
...
Caprice
20 days ago
A) Refer it to the Product Owner
upvoted 0 times
...