What is one way to determine if the Product Owner is interacting with the Developers enough throughout a Sprint?
(choose the best answer)
A. The Developers should determine the percentage of time the Product Owner is required to be present and monitor whether the Product Owner's average presence is around this figure.
Some reasons why the other options are not correct are:
C: Observe whether the Developers need to ask the Product Owner questions at times other than during the Daily Scrum. This option is not correct because it implies that asking questions is a sign of insufficient interaction, which may not be true. Asking questions is a natural and healthy part of communication and collaboration between the Product Owner and the Developers. It shows that they are engaged, curious, and willing to learn from each other. It also helps them to clarify requirements, expectations, and feedback, and to resolve any ambiguities or conflicts. Asking questions does not necessarily mean that there is a lack of interaction, but rather that there is a need for more information or clarification.
What is an Increment? | Scrum.org
What Is a Daily Standup? | A Guide to Running Effective Standup Meetings | Atlassian
An important aspect of Scrum are timeboxes. Select two ways in which timeboxing reinforces the creation of value.
(choose the best two answers)
C) Timeboxes encourage the people who are closest to the problem to create the best possible result in the time allotted, given the current context.
You are the Scrum Master for a Scrum Team whose Daily Scrum is scheduled to start at 10:00 each day. Developers routinely turn up late, and once everyone has assembled, the Daily Scrum starts. By then it is typically 4 to 5 minutes later than scheduled. Other meetings in the organization typically allow 4 to 5 minutes for people to transport within the building.
Some Developers complain that it is now hard to achieve the purpose of the Daily Scrum within the timebox, since there is only 10 or 11 minutes left after waiting for people to show up. The Developers ask for your advice.
(choose the best answer)
This is the best answer because it empowers the Developers to take ownership of their own process and find a solution that works for them. The Scrum Master can facilitate the discussion and help the Developers understand the value and importance of the Daily Scrum, but not impose or dictate any specific action or rule. The Scrum Master can also support the Developers in conducting an experiment and evaluating the results, if they decide to do so.
Scrum Guide 2020, page 13: ''The Scrum Master serves the Scrum Team in several ways, including coaching the team members in self-management and cross-functionality.''
Professional Scrum Master II Course, page 14: ''The Daily Scrum is a key opportunity for inspection and adaptation at the team level. It helps the team to synchronize their work, identify impediments, and collaborate on solutions.''
Professional Scrum Master II Course, page 21: ''The Scrum Master can help the team to resolve conflicts by facilitating dialogue, listening actively, asking powerful questions, and supporting collaborative decision making.''
True or False: During the Sprint Review of a scaled development effort, every Scrum Team should demonstrate its individual Increment separately.
During the Sprint Review of a scaled development effort, the Scrum Teams should demonstrate the integrated Increment that they have collectively delivered, not their individual Increments separately. This ensures that the stakeholders can provide feedback on the value and quality of the product as a whole, and that the Scrum Teams can inspect their alignment and collaboration.
Scrum Guide 2020, page 14: ''The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. The Scrum Team presents the results of their work to key stakeholders and progress toward the Product Goal is discussed.''
Nexus Guide 2020, page 7: ''The Nexus Sprint Review is an event where appropriate stakeholders review the Integrated Increment that has been built throughout the Sprint by all Scrum Teams in a Nexus.''
In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint, because the feedback from the user acceptance tests are disrupting work in Sprints. Is this a good idea?
(choose the best answer)
User acceptance testing is a process of verifying that the product meets the user's needs and expectations. It is an important feedback mechanism that helps the Scrum Team validate their assumptions, inspect the value and quality of the Increment, and adapt their plans accordingly. Scrum requires that the Increment be transparent, meaning that it is observable and understandable by anyone with a stake in the outcome. Scrum also requires that the feedback loop be short, meaning that the Scrum Team can receive and respond to feedback quickly and frequently.
Therefore, it is not a good idea to have user acceptance testing done every third Sprint, because:
The Increment will not be transparent (B), meaning that the Scrum Team and the stakeholders will not have a clear and shared understanding of what has been done and what remains to be done. This may lead to misalignment, confusion, or conflict over the product vision, scope, and quality.
The feedback loop is too long (B), meaning that the Scrum Team will not be able to inspect and adapt based on the user's feedback in a timely manner. This may lead to wasted effort, missed opportunities, or reduced value delivery.
The other options are not correct because:
It does not depend on what is stated in their Definition of Done (A), which is a formal description of the state of the Increment when it meets the quality standards required for the product. The Definition of Done does not dictate how or when user acceptance testing should be done, but rather what criteria must be met for the Increment to be considered ''Done''.
The Scrum Team is a self-managing team , which means that they have the autonomy and authority to organize and manage their own work within the boundaries of Scrum. However, this does not mean that they can ignore or postpone user feedback, which is essential for delivering value and satisfying customer needs.
The Scrum Team needs stability in the Sprint (D), which means that they need to have a clear and consistent Sprint Goal, Sprint Backlog, and Definition of Done throughout the Sprint. However, this does not mean that they need to avoid or resist user feedback, which is a source of learning and improvement for the product and the process.
Carmela
12 hours agoRodrigo
1 months agoFabiola
2 months agoJacquelyne
3 months agoAretha
3 months agoTammara
4 months agoLorenza
5 months agoDelsie
5 months agoOlive
5 months agoAudra
6 months agoJanae
6 months agoJess
6 months agoCristen
7 months agoTricia
7 months agoYesenia
7 months agoJoni
7 months agoJustine
8 months agoMicah
8 months agoLashawn
8 months agoMi
9 months agoGene
10 months agoIlene
10 months agoAlethea
12 months agoIsadora
12 months ago