During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out so
the Nexus can visualize dependencies. For example, PBI 5 for Team Orange is dependent on
Team Red completing PBI 1.
All else being equal, which PBI is most concerning?
(choose the best answer)
The other answers are not correct for the following reasons:
Glennis
3 days agoAdrianna
3 days agoDevon
6 days agoNorah
10 days ago