Scrum Exam PSPO-II Topic 1 Question 30 Discussion

Actual exam question for Scrum's PSPO-II exam
Question #: 30
Topic #: 1
[All PSPO-II Questions]

What typically happens if Product Backlog items are not sufficiently clear during Sprint

Planning?

(choose the best answer)

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Shizue
4 days ago
I don't think we need to look for a new Scrum Master and re-start the Sprint.
upvoted 0 times
...
Ivan
6 days ago
Maybe the meeting should be cancelled for refinement first.
upvoted 0 times
...
Josephine
14 days ago
I'm going with Option B. Unclear requirements are a recipe for confusion and chaos during Sprint Planning.
upvoted 0 times
Chau
2 days ago
Option B) The Developers will have difficulty creating a forecast of work for the Sprint.
upvoted 0 times
...
...
Jesusita
29 days ago
I agree, the Developers will struggle to forecast their work.
upvoted 0 times
...
Stephaine
1 months ago
Option C is a bit of a joke, right? 'Nothing in particular' happening when the backlog is unclear? That's a surefire way to end up in a dumpster fire.
upvoted 0 times
...
Tiffiny
1 months ago
Option E? Really? Cancelling the meeting and doing refinement first? That's like trying to fix a flat tire before you've even started driving.
upvoted 0 times
German
3 days ago
B) The Developers will have difficulty creating a forecast of work for the Sprint.
upvoted 0 times
...
Ronny
16 days ago
A) Nothing, so long as the Product Owner gives the Developers a clear Sprint Goal.
upvoted 0 times
...
...
James
1 months ago
Option B is the best answer. If the Product Backlog items are not clear, the Developers will struggle to forecast the work for the Sprint.
upvoted 0 times
Leeann
16 hours ago
A) Nothing, so long as the Product Owner gives the Developers a clear Sprint Goal.
upvoted 0 times
...
Raina
12 days ago
B) The Developers will have difficulty creating a forecast of work for the Sprint.
upvoted 0 times
...
...
Dominga
2 months ago
I think if Product Backlog items are not clear, it will be hard to plan the Sprint.
upvoted 0 times
...