True or False: A high-performance Scrum Team ensures that each Increment is complete by running a Release Sprint.
The concept of a ''Release Sprint'' is not found in the Scrum Guide or the Professional Scrum Product Owner (PSPO I) materials. Scrum does not require a separate Sprint for releasing an Increment. According to Scrum, each Increment must be usable and potentially releasable at the end of every Sprint, which means the product should be in a releasable state irrespective of whether the Product Owner decides to release it or not. The idea of a Release Sprint is not aligned with Scrum's principle of continuous delivery and the definition of ''Done''.