Scrum Exam PSPO-I Topic 1 Question 2 Discussion

Actual exam question for Scrum's PSPO-I exam
Question #: 2
Topic #: 1
[All PSPO-I Questions]

What is the timebox for the Sprint Review?

(choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: C

The timebox for the Sprint Review is four hours for a one-month Sprint. This is because:

The Sprint Review is an event where the Scrum Team and stakeholders inspect the Increment and adapt the Product Backlog if needed. The purpose of the Sprint Review is to elicit feedback and foster collaboration.

The timebox for each Scrum event is proportional to its frequency and duration. A one-month Sprint corresponds to a maximum calendar month.

The timebox for a one-month Sprint Review is four hours. For shorter Sprints, it is usually shorter.

The timebox ensures that there is enough time to inspect what has been done in relation to what could be done next and make any necessary adaptations to optimize value.

Other options, such as two hours for a one-month Sprint, one day, or as long as needed, are not valid answers as they do not reflect the correct timebox for the Sprint Review.


[Scrum Guide], page 17, section ''Sprint Review''

[Scrum Guide], page 9, section ''Sprint''

[Scrum Guide], page 9, section ''Timeboxing Scrum Events''

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77