Scrum Exam PSM-II Topic 5 Question 9 Discussion

Actual exam question for Scrum's PSM-II exam
Question #: 9
Topic #: 5
[All PSM-II Questions]

Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

Show Suggested Answer Hide Answer
Suggested Answer: B

Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.