Scrum Exam PSM-II Topic 5 Question 55 Discussion

Actual exam question for Scrum's PSM-II exam
Question #: 55
Topic #: 5
[All PSM-II Questions]

You are a Scrum Master and one of the Developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint, but regression testing is part of the Definition of Done. We have discussed with the Product Owner and during the Sprint we decided to change the Definition of Done to remove regression testing. Which two actions are appropriate in this situation?

(choose the best two answers)

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Brigette
26 days ago
Regression testing? That's like double-checking your homework before handing it in. I say we skip it and go straight to the final exam!
upvoted 0 times
...
Albert
28 days ago
Changing the Definition of Done on the fly? That's like trying to change the rules of chess mid-game. I'll go with option D to keep things in order.
upvoted 0 times
...
Aron
29 days ago
I'd go with option C. As the Scrum Master, I need to understand the problem they're trying to solve and whether the change will actually improve transparency and quality.
upvoted 0 times
Rasheeda
2 days ago
B) Ask the Developers and the Product Owner if removing regression testing from the Definition of Done allows the team to produce useful and valuable Increments at the end of every Sprint?
upvoted 0 times
...
Ricarda
13 days ago
C) Ask the Developers and the Product Owner what problem they are going to solve by altering the Definition of Done during the Sprint to remove regression testing. Will this raise transparency or improve quality?
upvoted 0 times
...
...
Vernell
1 months ago
I disagree with option A. Altering the Definition of Done during the Sprint is not a good practice, as it can compromise the quality of the product. Option D seems to be the best choice.
upvoted 0 times
...
Ardella
1 months ago
I think option B and C are the most appropriate actions here. We need to understand the rationale behind the change and how it will impact the quality and value of the Increments.
upvoted 0 times
Lorrie
3 days ago
C) Ask the Developers and the Product Owner what problem they are going to solve by altering the Definition of Done during the Sprint to remove regression testing. Will this raise transparency or improve quality?
upvoted 0 times
...
Lore
4 days ago
B) Ask the Developers and the Product Owner if removing regression testing from the Definition of Done allows the team to produce useful and valuable Increments at the end of every Sprint?
upvoted 0 times
...
...
Caren
2 months ago
Let's discuss if removing regression testing will still allow us to produce valuable Increments at the end of every Sprint.
upvoted 0 times
...
Blossom
2 months ago
Yes, we decided to remove regression testing from the Definition of Done during the Sprint.
upvoted 0 times
...
Caren
2 months ago
Have you discussed this with the Product Owner?
upvoted 0 times
...
Blossom
2 months ago
We are not completing regression testing for all selected Product Backlog items in the Sprint.
upvoted 0 times
...

Save Cancel