Scrum Exam PSM-II Topic 5 Question 51 Discussion

Actual exam question for Scrum's PSM-II exam
Question #: 51
Topic #: 5
[All PSM-II Questions]

You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Stella, an external specialist who is not a member of any of the four Scrum Teams. What would you consider acceptable solutions for the problem?

(choose the best three answers)

Show Suggested Answer Hide Answer
Suggested Answer: E

The Development Team owns the Definition of ''Done'' and is accountable for the quality of the Product Backlog items.


Contribute your Thoughts:

Anglea
1 months ago
G is intriguing - getting the Scrum teams to learn from Stella directly could be really effective. Hands-on training is always better than just bringing in more resources.
upvoted 0 times
Dahlia
1 days ago
That's a good point, it could help in the long term to have more expertise in Stella's domain within the Scrum Teams.
upvoted 0 times
...
Toi
2 days ago
We could also consider option F, asking Stella for a plan to hire and train additional people in her domain.
upvoted 0 times
...
Julieta
11 days ago
I agree, hands-on training is always better than just bringing in more resources.
upvoted 0 times
...
Fernanda
13 days ago
I agree, hands-on training is always better than just bringing in more resources.
upvoted 0 times
...
Carin
15 days ago
G is intriguing - getting the Scrum teams to learn from Stella directly could be really effective.
upvoted 0 times
...
Aja
15 days ago
G is intriguing - getting the Scrum teams to learn from Stella directly could be really effective.
upvoted 0 times
...
...
Nu
2 months ago
Haha, option E is like the Scrum version of 'Have you tried turning it off and on again?' Not the most elegant solution, but points for creativity!
upvoted 0 times
Maryann
4 days ago
G) Create a team with Stella and identify people from the Scrum Teams to temporarily work in Stella's domain to learn to better serve the existing teams
upvoted 0 times
...
Haley
18 days ago
F) Ask Stella for a plan to hire and train additional people in her domain, and in the meantime work with the Product Owner and Scrum Teams to re-prioritize the work so that tasks not depending on Stella can be done first
upvoted 0 times
...
Karl
24 days ago
B) Developers with an interest in Stella's domain could volunteer to take on this work in their respective Scrum Teams.
upvoted 0 times
...
...
Carin
2 months ago
I'm not sure merging all the teams into one giant team is the best idea. Seems like it could just create more chaos and coordination issues. Scaling Scrum frameworks might be worth exploring in C.
upvoted 0 times
Heidy
10 days ago
C) Investigate whether additional techniques or frameworks for scaling Scrum would be appropriate for these Scrum Teams.
upvoted 0 times
...
Emogene
16 days ago
F) Ask Stella for a plan to hire and train additional people in her domain, and in the meantime work with the Product Owner and Scrum Teams to re-prioritize the work so that tasks not depending on Stella can be done first.
upvoted 0 times
...
Teri
25 days ago
B) Developers with an interest in Stella's domain could volunteer to take on this work in their respective Scrum Teams.
upvoted 0 times
...
...
Tawna
2 months ago
F looks like the most comprehensive solution. Bringing in more resources and re-prioritizing the work to avoid Stella as a bottleneck is the smart play here.
upvoted 0 times
Lina
6 days ago
Working with the Product Owner and Scrum Teams to re-prioritize the work will help in managing the workload effectively.
upvoted 0 times
...
Aileen
10 days ago
It's important to make sure that tasks not depending on Stella can be done first to keep the work flowing smoothly.
upvoted 0 times
...
Barrett
13 days ago
I agree, having a plan to hire and train additional people in Stella's domain seems like a proactive approach to solving the issue.
upvoted 0 times
...
Jaclyn
14 days ago
F looks like the most comprehensive solution. Bringing in more resources and re-prioritizing the work to avoid Stella as a bottleneck is the smart play here.
upvoted 0 times
...
Alease
17 days ago
Yes, re-prioritizing the work and temporarily assigning team members to learn from Stella could help mitigate the impact of her full-time commitment.
upvoted 0 times
...
Johnathon
1 months ago
It's important to make sure that the work can continue smoothly even if Stella is not available full-time.
upvoted 0 times
...
Iluminada
1 months ago
I agree, having a plan to hire and train additional people in Stella's domain seems like a proactive approach to the problem.
upvoted 0 times
...
Stanton
1 months ago
F looks like the most comprehensive solution. Bringing in more resources and re-prioritizing the work to avoid Stella as a bottleneck is the smart play here.
upvoted 0 times
...
...
Harley
2 months ago
Option B is definitely the way to go. Developers can volunteer to learn Stella's domain and help out the teams. This will build cross-functional skills and relieve the bottleneck.
upvoted 0 times
Delsie
1 months ago
F) Ask Stella for a plan to hire and train additional people in her domain, and in the meantime work with the Product Owner and Scrum Teams to re-prioritize the work so that tasks not depending on Stella can be done first.
upvoted 0 times
...
Hector
2 months ago
B) Developers with an interest in Stella's domain could volunteer to take on this work in their respective Scrum Teams.
upvoted 0 times
...
...
Nana
2 months ago
I believe option F is the best solution, as it addresses the immediate need while also planning for the future.
upvoted 0 times
...
Leah
2 months ago
I agree with Elke, but I also think option G could be beneficial in the long run.
upvoted 0 times
...
Elke
2 months ago
I think option B could work, if developers are willing to take on Stella's work.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77