At the seventh Sprint Review, the stakeholders seem disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors may have led to this?
(choose the best three answers)
The Development Team owns the Definition of ''Done'' and is accountable for the quality of the Product Backlog items.