Scrum Exam PSM-II Topic 2 Question 54 Discussion

Actual exam question for Scrum's PSM-II exam
Question #: 54
Topic #: 2
[All PSM-II Questions]

User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What needs to be done?

(choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: E

The Development Team owns the Definition of ''Done'' and is accountable for the quality of the Product Backlog items.


Contribute your Thoughts:

Antonio
11 days ago
Letting the user documentation accumulate until the end is a recipe for disaster. That's just kicking the can down the road and will create a huge backlog of work.
upvoted 0 times
...
Mila
13 days ago
In that case, the team can collaborate with the Product Owner to ensure the documentation meets the required standards.
upvoted 0 times
...
Eulah
16 days ago
I agree that the Scrum Team is accountable for user documentation, even without a dedicated technical writer. The Developers should step up and take ownership of this task.
upvoted 0 times
...
Eloisa
18 days ago
But what if the Developers don't have the necessary skills to write user documentation?
upvoted 0 times
...
Mila
19 days ago
A) Your Scrum Team is still accountable for creating user documentation. In this case, the Developers will write it.
upvoted 0 times
...