Scrum Exam PSM-I Topic 5 Question 49 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 49
Topic #: 5
[All PSM-I Questions]

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Noble
1 months ago
The Scrum Master should be like a strict but loving parent, gently reminding everyone to do their chores... or else no dessert after the sprint review.
upvoted 0 times
Royal
5 days ago
E) All of the above
upvoted 0 times
...
Eveline
1 months ago
D) The Scrum Team
upvoted 0 times
...
Adela
1 months ago
C) The Scrum Master
upvoted 0 times
...
...
Gail
1 months ago
The Scrum Master should make sure everyone does their tasks, except for that one guy who always brings in doughnuts. He's on permanent doughnut duty.
upvoted 0 times
...
Terry
2 months ago
All of the above? What is this, a trick question? I'm just going to go with C and hope for the best.
upvoted 0 times
Tom
7 days ago
Yeah, the Scrum Master plays a crucial role in ensuring the team stays on track during the sprint.
upvoted 0 times
...
Jolene
10 days ago
I agree, the Scrum Master is there to facilitate and remove any obstacles that may prevent the team from completing their tasks.
upvoted 0 times
...
Cheryll
18 days ago
I think it's the Scrum Master's responsibility to make sure everyone on the team does their tasks.
upvoted 0 times
...
...
Hildred
2 months ago
Well, I guess the Product Owner could keep an eye on things, but that seems like a lot of micromanaging. I'd go with the Scrum Master on this one.
upvoted 0 times
I agree, the Scrum Master is responsible for ensuring everyone on the team is doing their tasks.
upvoted 0 times
...
Keith
2 days ago
It's important for the Scrum Master to facilitate communication and collaboration within the team.
upvoted 0 times
...
Eugene
3 days ago
The Scrum Team should be self-organizing and accountable for their own work.
upvoted 0 times
...
Sylvie
14 days ago
Yeah, the Scrum Master is there to support the team and remove any obstacles.
upvoted 0 times
...
France
30 days ago
The Scrum Master is responsible for ensuring everyone on the team does their tasks.
upvoted 0 times
...
...
Jerlene
2 months ago
The Scrum Team as a whole should be responsible for ensuring everyone completes their tasks. It's a team effort, after all.
upvoted 0 times
Jessenia
1 months ago
The Scrum Team should work together to make sure all tasks are completed.
upvoted 0 times
...
Jerry
2 months ago
The Scrum Master should ensure everyone on the team does their tasks.
upvoted 0 times
...
...
Christiane
2 months ago
I think the Scrum Master should make sure everyone on the team does their tasks. They're the ones responsible for facilitating the Scrum process, right?
upvoted 0 times
...
Penney
2 months ago
But shouldn't the Scrum Team as a whole be accountable for their own tasks?
upvoted 0 times
...
Devon
2 months ago
I agree with Margurite, the Scrum Master is responsible for ensuring tasks are completed.
upvoted 0 times
...
Margurite
3 months ago
C) The Scrum Master should make sure everyone on the scrum Team does their tasks for the sprint.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77