Scrum Exam PSM-I Topic 4 Question 85 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 85
Topic #: 4
[All PSM-I Questions]

When is it most appropriate for a Scrum Team to change the Definition of Done?

(choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: B

According to the Scrum Guide, the Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product1.The Definition of Done is created by the Developers and it is used to assess when work is complete on the product Increment1.

The Scrum Guide also states that the Definition of Done may vary significantly per Scrum Team, depending on the context.The Definition of Done evolves over time and becomes more stringent as the Scrum Team matures1. Therefore, it is important for the Scrum Team to regularly inspect and adapt the Definition of Done to reflect their current situation and needs.

The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint1.The Sprint Retrospective focuses on three questions: What went well in the Sprint? What could be improved? What will we commit to improve in the next Sprint?1These questions can help the Scrum Team identify potential changes to the Definition of Done that would increase the quality and value of the product.

Option A is incorrect because Product Backlog refinement is not a formal Scrum event, but rather an ongoing activity that can happen at any time during the Sprint1.Product Backlog refinement is mainly concerned with adding detail, estimates, and order to Product Backlog items1. Changing the Definition of Done during Product Backlog refinement could cause confusion and inconsistency among the Developers and the Product Owner.

Option C is incorrect because Sprint Planning is a time-boxed event that initiates a Sprint by defining a Sprint Goal and selecting Product Backlog items that deliver one coherent function1.Sprint Planning is based on the current state of the Product Backlog and the latest Definition of Done1. Changing the Definition of Done during Sprint Planning could disrupt the flow of the event and affect the scope and feasibility of the Sprint.

Option D is incorrect because prior to starting a new project is not a specific time in Scrum.Scrum does not prescribe any phases or stages for a project, but rather an empirical approach that relies on frequent inspection and adaptation of both the product and the process1. Changing the Definition of Done before starting a new project could be premature and irrelevant, as the Scrum Team may not have enough information or experience to define what 'Done' means for their product.


Contribute your Thoughts:

Meaghan
10 days ago
I think it could also be done during Product Backlog refinement, depending on the situation.
upvoted 0 times
...
Charlesetta
11 days ago
I agree with Annamaria, changing it during Sprint Planning makes more sense.
upvoted 0 times
...
Annamaria
13 days ago
I disagree, I believe it should be during Sprint Planning.
upvoted 0 times
...
Lisha
16 days ago
I think it's during Sprint Retrospective.
upvoted 0 times
...
Chan
20 days ago
Haha, this question is a real head-scratcher! I'm going to go with B) During the Sprint Retrospective, because that's where the magic happens - the team gets together, eats some leftover pizza, and decides how to make things even better next time. What could be more appropriate?
upvoted 0 times
...
Olive
23 days ago
Hmm, I'm not so sure. I think D) Prior to starting a new project is the best answer. You want to get the Definition of Done sorted out before you dive into a new endeavor, don't you? Otherwise, how will you know what 'done' even means?
upvoted 0 times
...
Malcolm
24 days ago
C) During Sprint Planning seems like the logical choice to me. That's when the team gets together to plan the next Sprint, so it makes sense to align the Definition of Done at that time.
upvoted 0 times
...
Bulah
26 days ago
I agree with Bethanie. The Sprint Retrospective is the perfect opportunity to review and refine the Definition of Done. It's all about continuous improvement, right?
upvoted 0 times
Stephanie
16 days ago
A) During Product Backlog refinement.
upvoted 0 times
...
...
Bethanie
1 months ago
I think B) During the Sprint Retrospective is the most appropriate time to change the Definition of Done. That's when the team can reflect on how the current Definition is working and make adjustments as needed.
upvoted 0 times
Tran
16 days ago
It's all about continuous improvement and making sure the team is aligned on what 'done' means.
upvoted 0 times
...
Frank
24 days ago
I think it's important for the team to regularly review and update the Definition of Done.
upvoted 0 times
...
Vi
25 days ago
I agree, the Sprint Retrospective is a good time to make changes.
upvoted 0 times
...
...

Save Cancel