True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull

system.

Show Suggested Answer Hide Answer
Suggested Answer: A

The primary effect of limiting Work in Progress (WIP) is to create a pull system. A pull system ensures that new work is only started when there is capacity, meaning that work is 'pulled' into the system when the team has the availability to do so. This approach prevents overloading the team and helps maintain a steady and predictable flow of work, aligning with the Kanban practices within the Scrum framework


Contribute your Thoughts:

Janella
4 days ago
I think the answer is A) True.
upvoted 0 times
...