Scrum Exam PSD Topic 1 Question 31 Discussion

Actual exam question for Scrum's PSD exam
Question #: 31
Topic #: 1
[All PSD Questions]

Several scrum teams share the scrum master. Developers of multiple teams approach the scrum master, because they need fulltime commitment from the same technical specialist for the next sprint. What should the scrum master consider for the response to this problem? Choose the two best answers.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

The working increment is the goal of the sprint and should be kept in mind. The self-managing aspect of the teams is also crucial to take in mind. Stable velocity and optimally used developers are not the scrum master's concern.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77