Question #: 7
Topic #: 4
[All SAFe-SGP Questions]

Which role in SAFe has content authority over the Agile Team's backlog?

Show Suggested Answer Hide Answer
Suggested Answer: A

The true statement about Lean-Agile development and contracting is A. Quality is built-in through collaboration and automation. Lean-Agile development is an iterative and incremental approach to software development that emphasizes flexibility, adaptability, and continuous improvement. Quality is not something that is added at the end of the development cycle, but rather something that is embedded throughout the process. Lean-Agile teams collaborate with customers and stakeholders to define clear and testable acceptance criteria for each work item.They also use automation tools to perform frequent testing, integration, and deployment of the software, ensuring that the solution meets the quality standards and compliance requirements12.

1:Advanced Topic - Agile Contracts - Scaled Agile Framework2:Government - Building in Quality and Compliance - Scaled Agile Framework


Contribute your Thoughts:

Tu
1 months ago
The Agile Team has content authority over their backlog? What is this, amateur hour? Clearly, the correct answer is B) Product Owner.
upvoted 0 times
...
Elly
1 months ago
As a certified SAFe expert, I can tell you with certainty that the Product Owner is the one with content authority over the Agile Team's backlog. It's kind of their whole job description.
upvoted 0 times
Blondell
5 days ago
So, if we have any questions or need clarification on the backlog, we should go to the Product Owner.
upvoted 0 times
...
Rene
6 days ago
That makes sense, since the Product Owner is responsible for prioritizing and managing the backlog.
upvoted 0 times
...
Luisa
16 days ago
Product Owner is definitely the one with content authority over the Agile Team's backlog.
upvoted 0 times
...
Kirk
25 days ago
That makes sense, the Product Owner is responsible for prioritizing and managing the backlog.
upvoted 0 times
...
Terrilyn
1 months ago
Product Owner is definitely the one with content authority over the Agile Team's backlog.
upvoted 0 times
...
...
Mabel
2 months ago
The Product Owner, of course. They're the ones who know the customer needs best and can make sure the backlog aligns with the product vision.
upvoted 0 times
Casie
24 days ago
A) Release Train Engineer
upvoted 0 times
...
Carma
1 months ago
That's correct! The Product Owner is responsible for prioritizing the backlog based on customer needs.
upvoted 0 times
...
Sang
1 months ago
B) Product Owner
upvoted 0 times
...
...
Dante
2 months ago
Wait, isn't the Agile Team supposed to have control over their own backlog? I'm going with D) Agile Team on this one.
upvoted 0 times
Hubert
2 days ago
Actually, the Agile Team is in charge of managing their own backlog.
upvoted 0 times
...
Janey
8 days ago
Product Management is responsible for prioritizing the backlog items.
upvoted 0 times
...
Chauncey
1 months ago
No, I believe it's the Release Train Engineer who has the final say on the backlog.
upvoted 0 times
...
Suzi
1 months ago
I think the Product Owner actually has content authority over the Agile Team's backlog.
upvoted 0 times
...
...
Clay
2 months ago
This one's tricky, but I think the correct answer is B) Product Owner. They're the ones responsible for prioritizing and managing the backlog.
upvoted 0 times
Lindsey
1 months ago
Yeah, the Product Owner is the one who decides what goes into the backlog and in what order.
upvoted 0 times
...
Socorro
1 months ago
I agree, the Product Owner is the one with content authority over the Agile Team's backlog.
upvoted 0 times
...
...
Moira
2 months ago
I'm pretty sure it's the Release Train Engineer who has the final say on the backlog. They're the ones managing the overall program, right?
upvoted 0 times
...
Nobuko
2 months ago
But doesn't the Release Train Engineer also play a role in coordinating the backlog priorities across multiple teams?
upvoted 0 times
...
Jacquelyne
2 months ago
The Product Owner definitely has content authority over the Agile Team's backlog. That's a core responsibility of the role.
upvoted 0 times
Isabella
13 days ago
B) Product Owner
upvoted 0 times
...
Erick
14 days ago
The Release Train Engineer facilitates the Agile Release Train, but the Product Owner has content authority over the backlog.
upvoted 0 times
...
Lenna
18 days ago
A) Release Train Engineer
upvoted 0 times
...
Jutta
1 months ago
That's correct! The Product Owner is responsible for prioritizing and managing the backlog.
upvoted 0 times
...
Kip
2 months ago
B) Product Owner
upvoted 0 times
...
...
Thersa
2 months ago
I agree with Gwenn, the Product Owner is responsible for prioritizing and managing the backlog.
upvoted 0 times
...
Gwenn
2 months ago
B) Product Owner has content authority over the Agile Team's backlog.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77