What goes into the Portfolio Backlog?
The Portfolio Backlog in SAFe contains the larger initiatives, known as Epics. Epics are substantial pieces of work that require analysis, investment, and development effort over multiple Program Increments (PIs). They represent significant business or technical needs that drive the long-term strategy of the organization. These Epics are prioritized and managed in the Portfolio Backlog, where they can be decomposed into smaller, actionable items as they progress through the development process.