Scaled Agile Exam SAFe-SASM Topic 1 Question 22 Discussion

Actual exam question for Scaled Agile's SAFe-SASM exam
Question #: 22
Topic #: 1
[All SAFe-SASM Questions]

What is the primary measurement during Inspect and Adapt?

Show Suggested Answer Hide Answer
Suggested Answer: A

The primary measurement during the Inspect and Adapt (I&A) event in SAFe is the program predictability measure. This metric assesses the Agile Release Train's (ART) ability to deliver on its commitments within a Program Increment (PI). It helps teams understand how accurately they can plan and execute work, providing a basis for continuous improvement. By focusing on predictability, organizations can improve their planning processes, align better with business objectives, and ensure more reliable delivery of value.


Contribute your Thoughts:

Jaclyn
6 days ago
I think it's definitely the Number of Features delivered. That's the whole point of Inspect and Adapt, right?
upvoted 0 times
...