SAP Exam E_S4HCON2023 Topic 1 Question 21 Discussion

Actual exam question for SAP's E_S4HCON2023 exam
Question #: 21
Topic #: 1
[All E_S4HCON2023 Questions]

You are performing an SAP S/4HANA conversion with the migration repetition option. After which phase does SUM stop to enable a test cycle?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Keva
14 hours ago
I'm confident that the answer is C. EU_CLONE_MIG_SOT_RUN. This phase is where SUM starts the migration and stops to allow for a test cycle before the final step.
upvoted 0 times
...
Emiko
8 days ago
Hmm, I'm not sure about this one. Let me re-read the question and the options. Wait, is this a trick question? What if the answer is actually a secret hidden in the question itself? *laughs*
upvoted 0 times
...
Nelida
13 days ago
I think the correct answer is D. EU_CLONE_MIG_DT_RUN. This phase is when SUM creates the migration dataset and stops to enable a test cycle before the final migration.
upvoted 0 times
...
Karma
23 days ago
I'm not sure, but I think D) EU_CLONE_MIG_DT_RUN could also be a possible answer.
upvoted 0 times
...
Kerrie
27 days ago
I agree with Artie, because after the EU_CLONE_MIG_SOT_RUN phase, SUM stops to enable a test cycle.
upvoted 0 times
...
Artie
30 days ago
I think the answer is C) EU_CLONE_MIG_SOT_RUN.
upvoted 0 times
...