Hmm, I'm not so sure about C. Requirement lead time seems more like a lead time for the actual demand, not the replenishment process. But the other three are definitely correct.
A, B, and D look like the right answers to me. The replenishment lead time should include the time it takes to process the purchase, the planned delivery time, and the time to process the goods receipt.
Fidelia
10 months agoFatima
10 months agoNobuko
10 months agoShayne
10 months agoMirta
10 months agoSantos
10 months agoNobuko
10 months agoFranchesca
10 months agoJosphine
11 months agoEmerson
11 months agoShannan
11 months agoNicholle
11 months agoLaura
11 months agoCarin
11 months agoDottie
11 months agoTamesha
11 months agoFrederick
11 months agoShelia
11 months agoRickie
11 months agoYasuko
12 months agoSylvia
12 months agoSolange
11 months agoCeleste
11 months agoVeronika
11 months agoDottie
12 months agoLoise
12 months agoTamesha
1 years agoYasuko
1 years ago