In the material master record there are three planned prices: ""Planned price 1"", ""Planned price 2""and""Planned price 3"". What do you use them for?
I'm going with option D. It just makes sense that the planned prices would be used to update the standard price during the release of a standard cost estimate. That's what they're for, right?
Hmm, I'm not sure. I thought the planned prices were used to update the standard price during the release of a standard cost estimate. But I could be wrong.
I think option B is the correct answer. The planned prices are used to valuate the materials in cost estimates, not for actual goods movements or stock valuation.
Felix
3 days agoEmiko
6 days agoStacey
22 days agoAmber
25 days agoBurma
16 hours agoLuisa
2 days agoMurray
28 days agoTayna
29 days agoBarbra
30 days ago