SAP Exam C_TS4CO_2021 Topic 4 Question 53 Discussion

Actual exam question for SAP's C_TS4CO_2021 exam
Question #: 53
Topic #: 4
[All C_TS4CO_2021 Questions]

Which statements best describes a single cost center standard hierarchy?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Desire
1 months ago
As an accountant, I live for these kinds of questions. It's like a secret language only we understand. D all the way, my friends!
upvoted 0 times
Zana
12 days ago
D) It is a structure to which all the cost centers within a controlling area are assigned.
upvoted 0 times
...
Pansy
17 days ago
C) It is a structure to which all the cost centers within an operating concern are assigned.
upvoted 0 times
...
Galen
23 days ago
B) It is a structure to which all cost center groups created within an operating concern are assigned.
upvoted 0 times
...
Aide
1 months ago
A) It is a structure to which all cost center groups create for a controlling area are assigned.
upvoted 0 times
...
...
Zana
2 months ago
Option D sounds like the winner to me. It's the only one that specifically mentions 'a controlling area', which seems to be the key element in a single cost center standard hierarchy.
upvoted 0 times
...
Ivette
2 months ago
Hmm, this is a tricky one. I was initially leaning towards B, but I think D is the better option. Gotta love these accounting questions, they really keep you on your toes!
upvoted 0 times
Yoko
11 days ago
Definitely, D is the most logical choice here.
upvoted 0 times
...
Joni
19 days ago
Yeah, D makes sense when you think about it.
upvoted 0 times
...
Lilli
28 days ago
I agree, D seems to be the best option.
upvoted 0 times
...
Page
1 months ago
I think D is the correct answer.
upvoted 0 times
...
...
Dean
2 months ago
I was a bit confused between options C and D, but after thinking it through, I believe D is the right choice. It's a structure for all cost centers within a controlling area.
upvoted 0 times
...
Amalia
2 months ago
I think option D is the correct answer here. A single cost center standard hierarchy is a structure that all the cost centers within a controlling area are assigned to.
upvoted 0 times
Mitsue
28 days ago
I'm leaning towards option B, as it mentions cost center groups within an operating concern.
upvoted 0 times
...
Lorrie
29 days ago
I believe it is option A, as it specifically mentions cost center groups within a controlling area.
upvoted 0 times
...
Barney
1 months ago
I think it could also be option C, as it mentions all the cost centers within an operating concern.
upvoted 0 times
...
Dominque
1 months ago
I agree, option D makes the most sense.
upvoted 0 times
...
...
Bronwyn
2 months ago
I'm not sure, but C also sounds plausible since it mentions operating concern.
upvoted 0 times
...
Emerson
2 months ago
I agree with Judy, D makes sense because it mentions controlling area.
upvoted 0 times
...
Judy
2 months ago
I think the answer is D.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77