SAP Exam C_TS452_2410 Topic 2 Question 3 Discussion

Actual exam question for SAP's C_TS452_2410 exam
Question #: 3
Topic #: 2
[All C_TS452_2410 Questions]

Which of the following procurement proposals can be created during an MRP Live planning run for

externally procured materials? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: C, D

Contribute your Thoughts:

Shawna
3 months ago
Hold on, hold on. Didn't they say there are 2 correct answers? I'm going with A) Planned order and D) Purchase requisition. Gotta read the question carefully, folks.
upvoted 0 times
Shaun
2 months ago
Yes, you're correct. Those are the two procurement proposals that can be created during an MRP Live planning run for externally procured materials.
upvoted 0 times
...
Vilma
3 months ago
I think you're right, A) Planned order and D) Purchase requisition are the correct answers.
upvoted 0 times
...
...
Shenika
3 months ago
I'm not sure about Purchase requisition. I think it's not created during an MRP Live planning run.
upvoted 0 times
...
Cherelle
3 months ago
Haha, this is easy! A) Planned order and B) Purchase order, of course. I'm the MRP master, baby!
upvoted 0 times
Harrison
2 months ago
That's correct! You really know your stuff.
upvoted 0 times
...
Harrison
2 months ago
A) Planned order and B) Purchase order
upvoted 0 times
...
...
Stephen
3 months ago
I agree with Lashandra. Planned order and Purchase order make sense for externally procured materials.
upvoted 0 times
...
Lennie
3 months ago
Definitely A) Planned order, that's a no-brainer. But I'm not sure about the other one. Maybe C) Delivery schedule line?
upvoted 0 times
Frank
2 months ago
B) Purchase order is not one of the correct answers.
upvoted 0 times
...
Cassie
2 months ago
C) Delivery schedule line could be the other correct answer.
upvoted 0 times
...
Craig
2 months ago
A) Planned order is definitely one of the correct answers.
upvoted 0 times
...
...
Lashandra
3 months ago
I think the correct answers are A) Planned order and B) Purchase order.
upvoted 0 times
...
Pearlene
3 months ago
I think both A) Planned order and D) Purchase requisition are the correct answers. MRP Live should generate planned orders and purchase requisitions for externally procured materials.
upvoted 0 times
Carla
2 months ago
It's important to have both planned orders and purchase requisitions created for externally procured materials in the planning process.
upvoted 0 times
...
Charisse
3 months ago
I think you're right, those are the two correct options for procurement proposals during an MRP Live planning run.
upvoted 0 times
...
Tish
3 months ago
MRP Live should definitely generate planned orders and purchase requisitions for externally procured materials.
upvoted 0 times
...
Alishia
3 months ago
I agree, A) Planned order and D) Purchase requisition are the correct answers.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77