SAP Exam C_TS422_2022 Topic 2 Question 28 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 28
Topic #: 2
[All C_TS422_2022 Questions]

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Alline
1 months ago
I'm going with B) Teardown time and D) Setup Time. Reducing those will definitely streamline the midpoint operations. Unless, of course, you're working with a teleportation device. Then the answer might be C) Move time!
upvoted 0 times
Robt
2 days ago
Haha, if only we had teleportation devices to reduce move time!
upvoted 0 times
...
Emilio
4 days ago
True, those are important time elements to focus on for efficiency.
upvoted 0 times
...
Jesusita
13 days ago
I agree, reducing teardown time and setup time will definitely help streamline operations.
upvoted 0 times
...
...
Tish
1 months ago
The time elements that can be reduced are B) Teardown time and D) Setup Time. Gotta love those optimization strategies!
upvoted 0 times
Celestina
7 days ago
Optimization strategies really help in reducing those time elements.
upvoted 0 times
...
Janna
18 days ago
Teardown time and Setup Time can be reduced with reduction strategy settings.
upvoted 0 times
...
...
Niesha
1 months ago
Ha! I bet the answer is C) Move time. Can't reduce the time it takes to move if you're stuck in traffic, right? Just kidding, I know it's B) and D).
upvoted 0 times
Vincent
2 days ago
You're right, those are the correct answers.
upvoted 0 times
...
Micah
3 days ago
I think it's B) Teardown time and D) Setup Time.
upvoted 0 times
...
...
Ethan
2 months ago
Definitely B) Teardown time and D) Setup Time. Minimizing these tasks can significantly improve the efficiency of the operations.
upvoted 0 times
...
Derick
2 months ago
I agree with both of you. Queue and Teardown time can be reduced with the right settings.
upvoted 0 times
...
Gennie
2 months ago
I think the correct answers are B) Teardown time and D) Setup Time. Reducing these time elements can help optimize the midpoint scheduled operations.
upvoted 0 times
Rolland
14 days ago
I think focusing on teardown time and setup time is key to reducing overall operation time.
upvoted 0 times
...
Kallie
15 days ago
Move time is important to consider as well when trying to improve efficiency.
upvoted 0 times
...
Merissa
19 days ago
Queue time can also be reduced with the right strategy settings.
upvoted 0 times
...
Steffanie
1 months ago
I agree, reducing teardown time and setup time can definitely help optimize operations.
upvoted 0 times
...
...
Lisha
2 months ago
I believe Setup Time can also be reduced with reduction strategy settings.
upvoted 0 times
...
Carisa
2 months ago
I think the time element that can be reduced is Teardown time.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77