Which dynamic modification levels can be set in the inspection plan? Note: There are 3 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, C, D

Dynamic modification levels in SAP QM determine the granularity at which inspection scope changes (e.g., reduced to full inspection) are applied in an inspection plan (transaction QP01):

Characteristic Level (A): Modification can occur at the individual characteristic level within an operation, allowing specific MICs to skip or intensify based on their quality history.

Inspection Lot Level (C): The entire inspection lot can be modified (e.g., skipped), based on the quality level for the material or combination (e.g., material/supplier).

Operation Level (D): Modification can apply to an operation, adjusting all characteristics within it based on performance (e.g., operation-specific skip).

Inspection Type Level (B): Inspection types define the process (e.g., 01 for GR), but dynamic modification is not set at this level; it's tied to plans or lots.

Work Center (E): Work centers are execution locations, not a level for dynamic modification in QM.

Thus, 'Characteristic level,' 'Inspection lot level,' and 'Operation level' are the correct answers.


Contribute your Thoughts:

Roosevelt
28 days ago
I'm pretty confident that A, B, and D are the right choices. Although, I have to admit, the work center option did make me chuckle. Gotta keep us on our toes, don't they?
upvoted 0 times
Roxane
10 hours ago
I think A, B, and D are correct too. Work center was a curveball.
upvoted 0 times
...
...
Kimbery
1 months ago
Haha, I bet the person who wrote this question was just trying to trip us up with that work center option. Nice try, but I'm not falling for it! A, B, and D are the winners here.
upvoted 0 times
Noel
4 days ago
Yeah, the work center option was definitely a tricky one.
upvoted 0 times
...
Bette
7 days ago
I agree, A, B, and D are the correct dynamic modification levels.
upvoted 0 times
...
...
Beth
1 months ago
I also think the inspection lot level could be another dynamic modification level that can be set in the inspection plan. It allows for adjustments based on the specific inspection lots being processed.
upvoted 0 times
...
Cheryll
1 months ago
I agree with Ashton. Those three levels make sense because they are directly related to the specific characteristics, types of inspections, and operations being performed.
upvoted 0 times
...
Glendora
1 months ago
This question is a piece of cake! Everyone knows the correct answers are A, B, and C. Dynamic modification at the inspection lot level? That's a no-brainer.
upvoted 0 times
Nan
8 hours ago
C) Inspection lot level
upvoted 0 times
...
Rhea
9 days ago
B) Inspection type level
upvoted 0 times
...
Fabiola
1 months ago
A) Characteristic level
upvoted 0 times
...
...
Svetlana
2 months ago
Hmm, I'm not so sure about E. Work center? That doesn't really make sense to me in the context of dynamic modification levels. I'd go with A, B, and C.
upvoted 0 times
...
Ashton
2 months ago
I think the dynamic modification levels in the inspection plan can be set at the characteristic level, inspection type level, and operation level.
upvoted 0 times
...
Mariko
2 months ago
I think A, B, and D are the correct answers. The inspection plan can definitely be modified at the characteristic, inspection type, and operation levels.
upvoted 0 times
Ty
17 days ago
Yes, those are the correct answers. The inspection plan can be modified at the characteristic, inspection type, and operation levels.
upvoted 0 times
...
Ty
1 months ago
I agree, A, B, and D are the correct options for dynamic modification levels in the inspection plan.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77