Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Shawnee
7 days ago
I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
...
Brigette
10 days ago
I'm not sure about C and E, but A, B, and D seem right to me.
upvoted 0 times
...
Tresa
13 days ago
Option B is incorrect. Activities with the 'Must start on' constraint don't necessarily have negative float time. It depends on the project schedule.
upvoted 0 times
...
Francine
16 days ago
I agree with Alton. A, B, and D make sense to me.
upvoted 0 times
...
Bulah
17 days ago
I think options A, C, and D are correct. Float time can be negative, the float time of WBS elements is calculated by extrapolation, and critical activities have a float time less than or equal to zero.
upvoted 0 times
...
Alton
22 days ago
I think A, B, and D are correct.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77