Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 7 Question 49 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 49
Topic #: 7
[All C_TS412_2021 Questions]

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Iola
1 months ago
This question is a real floater, isn't it? I better not sink my chances by getting this wrong!
upvoted 0 times
Henriette
24 days ago
D) By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Marjory
1 months ago
B) Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Wayne
1 months ago
A) Float time can be negative
upvoted 0 times
...
...
Shawnee
2 months ago
I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
Carin
29 days ago
User3: By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Brigette
1 months ago
User2: Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Margurite
1 months ago
User1: Float time can be negative
upvoted 0 times
...
...
Brigette
2 months ago
I'm not sure about C and E, but A, B, and D seem right to me.
upvoted 0 times
...
Tresa
2 months ago
Option B is incorrect. Activities with the 'Must start on' constraint don't necessarily have negative float time. It depends on the project schedule.
upvoted 0 times
Elenora
22 days ago
E) The maximum size of a free float is as large as the total float of an activity
upvoted 0 times
...
Emogene
28 days ago
C) The float time of WBS elements is calculated by extrapolation
upvoted 0 times
...
Alisha
1 months ago
A) Float time can be negative
upvoted 0 times
...
...
Francine
2 months ago
I agree with Alton. A, B, and D make sense to me.
upvoted 0 times
...
Bulah
2 months ago
I think options A, C, and D are correct. Float time can be negative, the float time of WBS elements is calculated by extrapolation, and critical activities have a float time less than or equal to zero.
upvoted 0 times
Adrianna
12 days ago
So, options A, C, and D are the correct statements about float time.
upvoted 0 times
...
Alethea
18 days ago
I think critical activities having a float time less than or equal to zero makes sense.
upvoted 0 times
...
Tomas
22 days ago
Yes, that's correct. The float time of WBS elements is indeed calculated by extrapolation.
upvoted 0 times
...
Elza
1 months ago
I agree with you, float time can definitely be negative.
upvoted 0 times
...
...
Alton
2 months ago
I think A, B, and D are correct.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77